Caltrans Logo

Local Match for CMAQ Park & Ride

Description: CMAQ funded project for construction of new Park-and-Ride facility on California City Blvd and Harvard Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City California City
Zip Code 93505
 
Senate District
18
Assembly District 36
Congressional District 23
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
Increased Ridership  3      
Reduced Emissions  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE BEVINS (760) 373-7297   PWDIR@CALIFORNIACITY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$27 $12 $39
Non-bond Funding
 
Total**** $27 $13 $40

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$27 $13 $40 $40 $40 $0
 
Total* $27 $13 $40 $40 $40 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/14/2013 

04/30/2014 
 

 
08/14/2013 

04/30/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/11/2013 

07/18/2014 
 

 
11/11/2013 

07/18/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
09/09/2013 

04/02/2014 
 

 
09/09/2013 

04/02/2014 
100   

 


Begin Construction Phase

End Construction Phase
09/08/2014 

11/18/2014 
08/20/2015 

08/20/2015 
01/01/2015 

08/31/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
11/28/2014 

12/31/2014 
08/20/2015 

03/06/2016 
08/31/2015 

02/11/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 3
Reduced Emissions 2

Bond Funding Cost
Adopted:
$26,806
Current Approved:
$38,521
Actual Expenditures:
$38,521

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31