Tippecanoe Interchange Improvements, Phase II

Description: Modification and realignment of westbound I-10 ramps and improve local streets.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Loma Linda, San Bernardino
Zip Code
 
Senate District
29
Assembly District 59, 62, 63
Congressional District 41, 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SANBAG ANDREA NIETO 909-884-8276   anieto@sanbag.ca.gov
Design (PS&E) Phase
SANBAG ANDREA NIETO 909-884-8276   anieto@sanbag.ca.gov
Right of Way Phase
SANBAG ANDREA NIETO 909-884-8276   anieto@sanbag.ca.gov
Construction Phase
SANBAG ANDREA NIETO 909-884-8276   anieto@sanbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$10,669 $-1,978 $8,691
Non-bond Funding
State/Federal*
$5,108 $0 $5,108
Local**
$44,012 $-1,532 $42,480
 
Total**** $59,789 $-3,510 $56,279

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$5,189 $0 $5,189 $3,090 $3,090 $2,099
Right of Way
$34,175 $0 $34,175 $33,300 $33,300 $875
Construction
$20,425 $-3,510 $16,915 $16,985 $16,985 $-70
 
Total* $59,789 $-3,510 $56,279 $53,375 $53,375 $2,904

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/19/2005 

01/27/2011 
03/20/2014 

03/20/2014 
12/19/2005 

01/27/2011 
100  12/20/2005 

01/27/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/03/2008 

01/28/2014 
03/20/2014 

03/20/2014 
12/03/2008 

01/28/2014 
100  12/03/2008 

01/28/2014 


Begin Right of Way Phase

End Right of Way Phase
01/27/2011 

01/27/2014 
03/20/2014 

03/20/2014 
01/27/2011 

01/27/2014 
100  01/27/2011 

01/27/2019 


-61 
Begin Construction Phase

End Construction Phase
08/06/2014 

02/01/2017 
03/20/2014 

03/20/2014 
08/06/2014 

02/01/2017 
100  10/01/2014 

06/01/2017 
-2 

-4 
Begin Closeout Phase

End Closeout Phase
02/02/2017 

08/01/2017 
03/20/2014 

 
02/02/2017 

08/01/2017 
100  01/01/2019 

06/30/2019 
-23 

-23 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1 1

Bond Funding Cost
Adopted:
$10,669,000
Current Approved:
$8,598,000
Actual Expenditures:
$8,597,548

 

Status as of December 31, 2023.