State Route 99 Ramp Improvements

Description: SR 99 from Hammer Lane Interchange to Austin Road Interchange. Installation of ramp meters at five interchanges of SR 99 with Hammer Lane, Cherokee Road, Waterloo Road, Fremont Street, and Austin Rd

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
10
 
 
County/State Route San Joaquin 99
Postmile Begin/End 4.5 23
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Scott Guidi (209) 948-7829   scott.guidi@dot.ca.gov
Design (PS&E) Phase
Caltrans Scott Guidi (209) 948-7829   scott.guidi@dot.ca.gov
Right of Way Phase
Caltrans Scott Guidi (209) 948-7829   scott.guidi@dot.ca.gov
Construction Phase
Caltrans Scott Guidi (209) 948-7829   scott.guidi@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$2,400 $-67 $2,333
Non-bond Funding
State/Federal*
$360 $0 $360
Local**
$280 $0 $280
 
Total**** $3,040 $-67 $2,973

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$130 $0 $130 $0 $0 $130
Design(PS&E)
$400 $0 $400 $0 $0 $400
Right of Way
$110 $0 $110 $0 $0 $110
Construction
$2,400 $-67 $2,333 $0 $0 $2,333
 
Total* $3,040 $-67 $2,973 $0 $0 $2,973

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2013 

01/06/2014 
05/21/2014 

05/21/2014 
12/01/2013 

01/06/2014 
100  12/01/2013 

01/06/2014 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2014 

05/15/2014 
05/21/2014 

05/21/2014 
01/01/2014 

05/15/2014 
100  01/01/2014 

05/15/2014 


Begin Right of Way Phase

End Right of Way Phase
02/01/2014 

04/01/2014 
05/21/2014 

05/21/2014 
02/01/2014 

04/01/2014 
100  02/01/2014 

04/01/2014 


Begin Construction Phase

End Construction Phase
08/18/2014 

08/18/2015 
05/21/2014 

05/21/2014 
08/18/2014 

08/18/2015 
100  12/24/2014 

10/30/2015 
-4 

-2 
Begin Closeout Phase

End Closeout Phase
09/01/2015 

05/01/2016 
05/21/2014 

 
09/01/2015 

05/01/2016 
50  09/01/2015 

05/01/2016 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 5 5

Bond Funding Cost
Adopted:
$2,400,000
Current Approved:
$2,333,000
Actual Expenditures:
$2,333,000

 

Status as of December 31, 2023.