Fairfield/Vacaville Intermodal Station Segment No. 2C

Description: In Fairfield, Six lane overpass for Peabody Road to replace the existing two lane at-grade crossing with the UPRR tracks, 6,650 ft. of new track, and new electronic switching gear

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Fairfield
Zip Code
 
Senate District
03
Assembly District 11
Congressional District 03
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  1.26    1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fairfield Ryan N. Panganiban 707-428-7017   rpanganiban@fairfield.ca.gov
Design (PS&E) Phase
City of Fairfield Ryan N. Panganiban 707-428-7017   rpanganiban@fairfield.ca.gov
Right of Way Phase
City of Fairfield Ryan N. Panganiban 707-428-7017   rpanganiban@fairfield.ca.gov
Construction Phase
City of Fairfield Ryan N. Panganiban 707-428-7017   rpanganiban@fairfield.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$11,000 $0 $11,000
Non-bond Funding
Local**
$11,600 $0 $11,600
 
Total**** $22,600 $0 $22,600

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$22,600 $0 $22,600 $22,600 $22,600 $0
 
Total* $22,600 $0 $22,600 $22,600 $22,600 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2009 

06/01/2010 
08/20/2014 

08/20/2014 
06/01/2009 

06/01/2010 
100  06/01/2009 

06/01/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/20/2009 

07/22/2014 
08/20/2014 

08/20/2014 
10/20/2009 

07/22/2014 
100  10/20/2009 

07/22/2014 


Begin Right of Way Phase

End Right of Way Phase
12/15/2009 

02/11/2014 
08/20/2014 

08/20/2014 
12/15/2009 

02/11/2014 
100  12/15/2009 

02/11/2014 


Begin Construction Phase

End Construction Phase
12/02/2014 

11/01/2016 
08/20/2014 

08/20/2014 
12/02/2014 

11/01/2016 
100  11/18/2014 

03/31/2018 


-17 
Begin Closeout Phase

End Closeout Phase
12/01/2016 

03/01/2017 
08/20/2014 

 
12/01/2016 

03/01/2017 
100  03/31/2018 

06/30/2018 
-16 

-16 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 1.26 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$11,000,000
Current Approved:
$11,000,000
Actual Expenditures:
$11,000,000

 

Status as of December 31, 2023.