Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Fairfield/Vacaville Intermodal Station Segment No. 2C |
Description: In Fairfield, Six lane overpass for Peabody Road to replace the existing two lane at-grade crossing with the UPRR tracks, 6,650 ft. of new track, and new electronic switching gear
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Solano |
City | Fairfield |
Zip Code | |
Senate District |
03 |
Assembly District | 11 |
Congressional District | 03 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 1.26 | 1 |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Fairfield | Ryan N. Panganiban | 707-428-7017 | rpanganiban@fairfield.ca.gov | |
Design (PS&E) Phase |
City of Fairfield | Ryan N. Panganiban | 707-428-7017 | rpanganiban@fairfield.ca.gov | |
Right of Way Phase |
City of Fairfield | Ryan N. Panganiban | 707-428-7017 | rpanganiban@fairfield.ca.gov | |
Construction Phase |
City of Fairfield | Ryan N. Panganiban | 707-428-7017 | rpanganiban@fairfield.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$11,000 | $0 | $11,000 | ||||
Non-bond Funding | |||||||
Local** |
$11,600 | $0 | $11,600 | ||||
Total**** | $22,600 | $0 | $22,600 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$22,600 | $0 | $22,600 | $22,600 | $22,600 | $0 | |
Total* | $22,600 | $0 | $22,600 | $22,600 | $22,600 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2009 06/01/2010 |
08/20/2014 08/20/2014 |
06/01/2009 06/01/2010 |
100 | 06/01/2009 06/01/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/20/2009 07/22/2014 |
08/20/2014 08/20/2014 |
10/20/2009 07/22/2014 |
100 | 10/20/2009 07/22/2014 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/15/2009 02/11/2014 |
08/20/2014 08/20/2014 |
12/15/2009 02/11/2014 |
100 | 12/15/2009 02/11/2014 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/02/2014 11/01/2016 |
08/20/2014 08/20/2014 |
12/02/2014 11/01/2016 |
100 | 11/18/2014 03/31/2018 |
0 -17 |
Begin Closeout Phase
End Closeout Phase |
12/01/2016 03/01/2017 |
08/20/2014 |
12/01/2016 03/01/2017 |
100 | 03/31/2018 06/30/2018 |
-16 -16 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 1.26 | 1 |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$11,000,000 |
Current Approved: |
$11,000,000 |
Actual Expenditures: |
$11,000,000 |
Status as of December 31, 2023.