Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
SR-905/SR-125 Northbound Connectors |
Description: In and near San Diego at State Route 11/125/905 separation. Construct SR 905/125 Northbound Connectors.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
11 |
County/State Route | San Diego 125 |
Postmile Begin/End | 0.1 1.7 |
County/State Route | San Diego 11 |
Postmile Begin/End | 0.4 1.6 |
County/State Route | San Diego 905 |
Postmile Begin/End | 9.6 11.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Ismael Salazar | 619-688-6766 | ismael.salazar@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Ismael Salazar | 619-688-6766 | ismael.salazar@dot.ca.gov | |
Right of Way Phase |
Caltrans | Ismael Salazar | 619-688-6766 | ismael.salazar@dot.ca.gov | |
Construction Phase |
Caltrans | Ismael Salazar | 619-688-6766 | ismael.salazar@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$20,021 | $-6,302 | $13,719 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,436 | $-1,096 | $2,340 | ||||
Local** |
$2,700 | $0 | $2,700 | ||||
Total**** | $26,157 | $-7,398 | $18,759 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$2,700 | $0 | $2,700 | $2,621 | $0 | $2,700 | |
Right of Way |
$800 | $-279 | $521 | $521 | $0 | $521 | |
Construction |
$22,657 | $-7,119 | $15,538 | $15,101 | $0 | $15,538 | |
Total* | $26,157 | $-7,398 | $18,759 | $18,243 | $0 | $18,759 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/02/2013 |
08/20/2014 |
10/02/2013 |
100 | 10/02/2013 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/28/2013 08/14/2014 |
08/20/2014 08/20/2014 |
03/28/2013 08/14/2014 |
100 | 03/28/2013 08/14/2014 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
03/28/2013 08/14/2014 |
08/20/2014 08/20/2014 |
03/28/2013 08/14/2014 |
100 | 03/28/2013 08/14/2014 |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2015 10/19/2016 |
08/20/2014 08/20/2014 |
07/01/2015 10/19/2016 |
100 | 07/31/2015 08/01/2017 |
-1 -10 |
Begin Closeout Phase
End Closeout Phase |
10/20/2016 10/21/2017 |
08/20/2014 |
10/20/2016 10/21/2017 |
50 | 08/01/2017 10/21/2017 |
-9 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$20,021,000 |
Current Approved: |
$13,719,000 |
Actual Expenditures: |
$13,334,003 |
Status as of December 31, 2023.