Caltrans Logo

SR-905/SR-125 Northbound Connectors

Description: In and near San Diego at State Route 11/125/905 separation. Construct SR 905/125 Northbound Connectors.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
11
 
 
County/State Route San Diego 125
Postmile Begin/End 0.1 1.7
 
County/State Route San Diego 11
Postmile Begin/End 0.4 1.6
 
County/State Route San Diego 905
Postmile Begin/End 9.6 11.4
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Ismael Salazar 619-688-6766   ismael.salazar@dot.ca.gov
Design (PS&E) Phase
Caltrans Ismael Salazar 619-688-6766   ismael.salazar@dot.ca.gov
Right of Way Phase
Caltrans Ismael Salazar 619-688-6766   ismael.salazar@dot.ca.gov
Construction Phase
Caltrans Ismael Salazar 619-688-6766   ismael.salazar@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$20,021 $-6,302 $13,719
Non-bond Funding
State/Federal*
$3,436 $-1,096 $2,340
Local**
$2,700 $0 $2,700
 
Total**** $26,157 $-7,398 $18,759

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,700 $0 $2,700 $2,621 $0 $2,700
Right of Way
$800 $-279 $521 $521 $0 $521
Construction
$22,657 $-7,119 $15,538 $15,101 $0 $15,538
 
Total* $26,157 $-7,398 $18,759 $18,243 $0 $18,759

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

10/02/2013 
 

08/20/2014 
 

10/02/2013 
100   

10/02/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/28/2013 

08/14/2014 
08/20/2014 

08/20/2014 
03/28/2013 

08/14/2014 
100  03/28/2013 

08/14/2014 


Begin Right of Way Phase

End Right of Way Phase
03/28/2013 

08/14/2014 
08/20/2014 

08/20/2014 
03/28/2013 

08/14/2014 
100  03/28/2013 

08/14/2014 


Begin Construction Phase

End Construction Phase
07/01/2015 

10/19/2016 
08/20/2014 

08/20/2014 
07/01/2015 

10/19/2016 
100  07/31/2015 

08/01/2017 
-1 

-10 
Begin Closeout Phase

End Closeout Phase
10/20/2016 

10/21/2017 
08/20/2014 

 
10/20/2016 

10/21/2017 
50  08/01/2017 

10/21/2017 
-9 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1 1

Bond Funding Cost
Adopted:
$20,021,000
Current Approved:
$13,719,000
Actual Expenditures:
$13,334,003

 

Status as of December 31, 2023.