Sanborn Rd/US101 Interchange Improvements and Elvee Drive Extension |
Description: Improve interchange, widen Elvee Drive, instrall ramp metering
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Monterey |
City | Monterey, Salinas |
Zip Code | 93905 |
Senate District |
12 |
Assembly District | 30 |
Congressional District | 20 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Salinas | Eda Herrera | 831-758-7438 | eda@ci.salinas.ca.us | |
Design (PS&E) Phase |
City of Salinas | Eda Herrera | 831-758-7438 | eda@ci.salinas.ca.us | |
Right of Way Phase |
City of Salinas | Eda Herrera | 831-758-7438 | eda@ci.salinas.ca.us | |
Construction Phase |
City of Salinas | Eda Herrera | 831-758-7438 | eda@ci.salinas.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$1,700 | $0 | $1,700 | ||||
Non-bond Funding | |||||||
Local** |
$2,400 | $200 | $2,600 | ||||
Total**** | $4,100 | $200 | $4,300 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $1,868 | $1,868 | $-1,868 | |
Right of Way |
$0 | $0 | $0 | $1 | $1 | $-1 | |
Construction |
$4,100 | $200 | $4,300 | $13,803 | $8,207 | $-3,907 | |
Total* | $4,100 | $200 | $4,300 | $15,672 | $10,076 | $-5,776 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/08/2013 05/06/2014 |
|
04/08/2013 05/06/2014 |
100 | 04/08/2013 05/06/2014 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/15/2013 06/01/2014 |
01/22/2015 |
10/15/2013 02/03/2015 |
100 | 10/15/2013 02/03/2015 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/15/2013 08/01/2014 |
|
12/15/2013 08/01/2014 |
100 | 12/15/2013 08/14/2014 |
0 0 |
Begin Construction Phase
End Construction Phase |
11/01/2014 10/30/2015 |
01/22/2015 01/22/2015 |
05/26/2015 05/26/2016 |
100 | 06/01/2016 06/23/2020 |
-12 -50 |
Begin Closeout Phase
End Closeout Phase |
11/01/2015 11/30/2015 |
01/22/2015 |
06/26/2016 07/26/2016 |
100 | 09/14/2020 11/16/2020 |
-51 -52 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,700,000 |
Current Approved: |
$1,700,000 |
Actual Expenditures: |
$1,700,000 |
Status as of December 31, 2023.