Caltrans Logo

Sanborn Rd/US101 Interchange Improvements and Elvee Drive Extension

Description: Improve interchange, widen Elvee Drive, instrall ramp metering

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Monterey
City Monterey, Salinas
Zip Code 93905
 
Senate District
12
Assembly District 30
Congressional District 20
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Salinas Eda Herrera 831-758-7438   eda@ci.salinas.ca.us
Design (PS&E) Phase
City of Salinas Eda Herrera 831-758-7438   eda@ci.salinas.ca.us
Right of Way Phase
City of Salinas Eda Herrera 831-758-7438   eda@ci.salinas.ca.us
Construction Phase
City of Salinas Eda Herrera 831-758-7438   eda@ci.salinas.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$1,700 $0 $1,700
Non-bond Funding
Local**
$2,400 $200 $2,600
 
Total**** $4,100 $200 $4,300

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $1,868 $1,868 $-1,868
Right of Way
$0 $0 $0 $1 $1 $-1
Construction
$4,100 $200 $4,300 $13,803 $8,207 $-3,907
 
Total* $4,100 $200 $4,300 $15,672 $10,076 $-5,776

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/08/2013 

05/06/2014 
 

 
04/08/2013 

05/06/2014 
100  04/08/2013 

05/06/2014 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/15/2013 

06/01/2014 
 

01/22/2015 
10/15/2013 

02/03/2015 
100  10/15/2013 

02/03/2015 


Begin Right of Way Phase

End Right of Way Phase
12/15/2013 

08/01/2014 
 

 
12/15/2013 

08/01/2014 
100  12/15/2013 

08/14/2014 


Begin Construction Phase

End Construction Phase
11/01/2014 

10/30/2015 
01/22/2015 

01/22/2015 
05/26/2015 

05/26/2016 
100  06/01/2016 

06/23/2020 
-12 

-50 
Begin Closeout Phase

End Closeout Phase
11/01/2015 

11/30/2015 
01/22/2015 

 
06/26/2016 

07/26/2016 
100  09/14/2020 

11/16/2020 
-51 

-52 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1 1

Bond Funding Cost
Adopted:
$1,700,000
Current Approved:
$1,700,000
Actual Expenditures:
$1,700,000

 

Status as of December 31, 2023.