Southbound State Route 99 from Hammer Lane to Fremont Street Interchange Ramp Meterin |
Description: Install ramp meeting systems, CCTVs, and MVPs
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr of Facilities Modified | 6 | 6 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Joy Pinne | 209-948-7854 | joy.pinne@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Joy Pinne | 209-948-7854 | joy.pinne@dot.ca.gov | |
Right of Way Phase |
Caltrans | Joy Pinne | 209-948-7854 | joy.pinne@dot.ca.gov | |
Construction Phase |
Caltrans | Joy Pinne | 209-948-7854 | joy.pinne@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$2,000 | $0 | $2,000 | ||||
Non-bond Funding | |||||||
Total**** | $2,000 | $0 | $2,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,000 | $0 | $2,000 | $1,496 | $0 | $2,000 | |
Total* | $2,000 | $0 | $2,000 | $1,496 | $0 | $2,000 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/10/2014 09/29/2014 |
|
07/10/2014 09/29/2014 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2014 12/31/2014 |
|
09/30/2014 12/31/2014 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
09/30/2014 10/15/2014 |
|
09/30/2014 10/15/2014 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/24/2015 07/24/2016 |
|
06/24/2015 07/24/2016 |
100 | 06/24/2015 02/12/2017 |
0 -7 |
Begin Closeout Phase
End Closeout Phase |
08/24/2016 08/24/2017 |
|
08/24/2016 08/24/2017 |
50 | 08/24/2017 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr of Facilities Modified | 6 | 6 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,000,000 |
Current Approved: |
$2,000,000 |
Actual Expenditures: |
$1,496,146 |
Status as of December 31, 2023.