YTI Terminal Enhancement & Truck Trip Reduction Program

Description: On-Dock railyard & Berth/Wharf Expansions

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Nbr Terminals Modified  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Los Angeles Ed Han 310-732-0395   ehan@portla.org
Design (PS&E) Phase
Port of Los Angeles Ed Han 310-732-0395   ehan@portla.org
Right of Way Phase
Port of Los Angeles Ed Han 310-732-0395   ehan@portla.org
Construction Phase
Port of Los Angeles Ed Han 310-732-0395   ehan@portla.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$9,533 $0 $9,533
Non-bond Funding
Local**
$321,665 $-280,000 $41,665
 
Total**** $331,198 $-280,000 $51,198

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,600 $0 $2,600 $0 $0 $2,600
Design(PS&E)
$2,906 $0 $2,906 $0 $0 $2,906
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$325,692 $-280,000 $45,692 $0 $0 $45,692
 
Total* $331,198 $-280,000 $51,198 $0 $0 $51,198

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/06/2013 

11/07/2014 
 

 
02/06/2013 

11/07/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/15/2013 

10/01/2015 
 

 
04/15/2013 

10/01/2015 
100   

10/01/2015 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/14/2015 

05/12/2017 
 

 
07/14/2015 

05/12/2017 
100  03/01/2016 

03/01/2018 
-8 

-10 
Begin Closeout Phase

End Closeout Phase
12/01/2016 

05/31/2018 
 

 
12/01/2016 

05/31/2018 
 

06/30/2018 


-1 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Nbr Terminals Modified 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.