I-10 Pepper Avenue Interchange

Description: Widen Pepper Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
SANBAG Paul Melocoton 909-884-8276   pmelocoton@sanbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$1,158 $0 $1,158
Non-bond Funding
State/Federal*
$904 $0 $904
Local**
$6,626 $-64 $6,562
Private***
$1,487 $0 $1,487
 
Total**** $10,175 $-64 $10,111

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$64 $0 $64 $64 $64 $0
Design(PS&E)
$561 $0 $561 $817 $817 $-256
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$9,550 $-64 $9,486 $8,995 $8,995 $491
 
Total* $10,175 $-64 $10,111 $9,876 $9,876 $235

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/09/2013 

02/20/2015 
 

 
07/09/2013 

02/20/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/25/2014 

04/13/2015 
 

 
03/25/2014 

04/13/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/20/2015 

04/13/2015 
 

 
02/20/2015 

04/13/2015 
100   

 


Begin Construction Phase

End Construction Phase
10/07/2015 

08/17/2017 
 

 
10/07/2015 

08/17/2017 
100  10/07/2015 

05/31/2018 


-10 
Begin Closeout Phase

End Closeout Phase
08/17/2017 

08/17/2018 
 

 
08/17/2017 

08/17/2018 
75  06/01/2018 

12/31/2022 
-10 

-53 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1

Bond Funding Cost
Adopted:
$1,158,000
Current Approved:
$1,158,000
Actual Expenditures:
$1,008,046

 

Status as of December 31, 2023.