Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
San Francisco Bay to Stockton Ship Channel Deepening Project |
Description: Increase Depth of the Stockton Ship Channel
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Joaquin |
City | Stockton |
Zip Code | |
Senate District |
05 |
Assembly District | 17, 26 |
Congressional District | 11, 18 |
Caltrans District |
10 |
County/State Route | San Joaquin 4 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Miles of Channels Dredged | 65 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Stockton | Juan Villanueva | (209) 946-0246 | jvillanueva@stocktonport.com | |
Design (PS&E) Phase |
Port of Stockton | Juan Villanueva | (209) 946-0246 | jvillanueva@stocktonport.com | |
Right of Way Phase |
Port of Stockton | Juan Villanueva | (209) 946-0246 | jvillanueva@stocktonport.com | |
Construction Phase |
Port of Stockton | Juan Villanueva | (209) 946-0246 | jvillanueva@stocktonport.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$17,500 | $-10,300 | $7,200 | ||||
Ports Inf, Sec, & AQ |
$123,947 | $-123,947 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $7,200 | $7,200 | ||||
Local** |
$0 | $600 | $600 | ||||
Total**** | $141,447 | $-126,447 | $15,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$3,668 | $-3,568 | $100 | $3,317 | $3,317 | $-3,217 | |
Design(PS&E) |
$1,000 | $-500 | $500 | $0 | $0 | $500 | |
Right of Way |
$800 | $-800 | $0 | $0 | $0 | $0 | |
Construction |
$135,979 | $-121,579 | $14,400 | $6,284 | $6,284 | $8,116 | |
Total* | $141,447 | $-126,447 | $15,000 | $9,602 | $9,602 | $5,398 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/15/2008 09/22/2011 |
04/25/2012 |
03/15/2008 08/07/2008 |
100 | 03/15/2008 03/06/2012 |
0 -44 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/29/2011 03/01/2012 |
04/25/2012 04/25/2012 |
11/01/2011 02/15/2012 |
100 | 11/01/2011 02/25/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
03/10/2012 06/01/2012 |
04/25/2012 04/25/2012 |
03/10/2012 06/01/2012 |
100 | 04/25/2012 04/25/2012 |
-2 1 |
Begin Construction Phase
End Construction Phase |
06/01/2012 11/30/2014 |
04/25/2012 04/25/2012 |
08/01/2012 11/30/2013 |
100 | 06/29/2012 11/30/2021 |
1 -97 |
Begin Closeout Phase
End Closeout Phase |
11/30/2014 06/30/2015 |
04/25/2012 |
11/30/2013 06/30/2014 |
75 | 11/30/2020 03/28/2023 |
-85 -106 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Miles of Channels Dredged | 65 |
Bond Funding Cost | |
---|---|
Adopted: |
$141,447,000 |
Current Approved: |
$7,200,000 |
Actual Expenditures: |
$6,284,361 |
Status as of December 31, 2023.