Citrus Avenue Crossing Improvements

Description: At-Grade crossing improvements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Nbr of Facilities Modified  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$1,455 $0 $1,455
Non-bond Funding
Local**
$2,030 $0 $2,030
 
Total**** $3,485 $0 $3,485

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$250 $0 $250 $0 $0 $250
Design(PS&E)
$325 $0 $325 $0 $0 $325
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,910 $0 $2,910 $0 $0 $2,910
 
Total* $3,485 $0 $3,485 $0 $0 $3,485

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2015 

10/31/2015 
 

 
08/01/2015 

10/31/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2015 

05/31/2016 
 

 
08/01/2015 

05/31/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/30/2016 

04/30/2018 
 

 
10/30/2016 

04/30/2018 
96   

06/30/2018 


-2 
Begin Closeout Phase

End Closeout Phase
05/01/2018 

04/30/2019 
 

 
05/01/2018 

04/30/2019 
 

06/30/2019 


-2 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Nbr of Facilities Modified 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.