Control Point Soledad Speed Increase |
Description: Track improvements
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr of Facilities Modified | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
SCRRA | Liz Lun | 909-593-6419 | lune@scrra.net | |
Design (PS&E) Phase |
SCRRA | Liz Lun | 909-593-6419 | lune@scrra.net | |
Right of Way Phase |
SCRRA | Liz Lun | 909-593-6419 | lune@scrra.net | |
Construction Phase |
SCRRA | Liz Lun | 909-593-6419 | lune@scrra.net | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$2,708 | $0 | $2,708 | ||||
Non-bond Funding | |||||||
Local** |
$3,940 | $0 | $3,940 | ||||
Total**** | $6,648 | $0 | $6,648 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$616 | $0 | $616 | $0 | $0 | $616 | |
Design(PS&E) |
$616 | $0 | $616 | $0 | $0 | $616 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$5,416 | $0 | $5,416 | $0 | $0 | $5,416 | |
Total* | $6,648 | $0 | $6,648 | $0 | $0 | $6,648 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/01/2015 10/31/2015 |
|
08/01/2015 10/31/2015 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2015 05/31/2016 |
|
08/01/2015 05/31/2016 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2016 04/30/2018 |
|
10/01/2016 04/30/2018 |
95 | 06/30/2018 |
0 -2 |
Begin Closeout Phase
End Closeout Phase |
05/01/2018 04/30/2019 |
|
05/01/2018 04/30/2019 |
0 | 09/30/2019 |
0 -5 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr of Facilities Modified | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.