Fullerton Road Grade Separation

Description: Construct 6 lane roadway underpass with retaining walls and new railroad bridge.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City City Of Industry
Zip Code
 
Senate District
22
Assembly District 57
Congressional District 32
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
ACE Martin Moreno (626) 696-9104   mmoreno@sgvcog.org
Design (PS&E) Phase
ACE Martin Moreno (626) 696-9104   mmoreno@sgvcog.org
Right of Way Phase
ACE Martin Moreno (626) 696-9104   mmoreno@sgvcog.org
Construction Phase
ACE Martin Moreno (626) 696-9104   mmoreno@sgvcog.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$35,060 $0 $35,060
Non-bond Funding
State/Federal*
$23,306 $0 $23,306
Local**
$50,730 $0 $50,730
Private***
$4,508 $0 $4,508
 
Total**** $113,604 $0 $113,604

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$11,107 $0 $11,107 $10,698 $10,698 $409
Right of Way
$32,123 $0 $32,123 $32,123 $30,772 $1,351
Construction
$70,374 $0 $70,374 $131,970 $215,428 $-145,054
 
Total* $113,604 $0 $113,604 $174,791 $256,898 $-143,294

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/30/2012 

10/31/2013 
 

 
11/30/2012 

10/31/2013 
100  04/15/2013 

10/31/2013 
-4 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2013 

11/30/2015 
 

 
11/30/2013 

11/30/2015 
100  11/01/2012 

11/30/2015 
13 

Begin Right of Way Phase

End Right of Way Phase
11/30/2013 

10/30/2015 
 

 
11/30/2013 

10/30/2015 
100  11/30/2013 

10/30/2015 


Begin Construction Phase

End Construction Phase
03/30/2016 

12/30/2019 
 

 
03/30/2016 

12/30/2019 
62  07/30/2016 

06/30/2025 
-4 

-67 
Begin Closeout Phase

End Closeout Phase
01/30/2020 

07/30/2020 
 

 
01/30/2020 

07/30/2020 
12/01/2025 

06/01/2026 
-71 

-71 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.