Cool Port Oakland

Description: Construction of a state-of-the-art temperature-controlled transload facility; 11,200 feet of rail track at Maritime Support Center.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Alameda
City Oakland
Zip Code 94607
 
Senate District
09
Assembly District 18
Congressional District 13
 
Caltrans District
04
 
 
County/State Route Alameda N/A
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  11,200 lf      
Nbr of Facilities Modified  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Oakland Pia Franzese (510)627-1154   pfranzese@portoakland
Design (PS&E) Phase
Port of Oakland Pia Franzese (510)627-1154   pfranzese@portoakland
Right of Way Phase
CPUC Pia Franzese (510)627-1154   pfranzese@portoakland
Construction Phase
Port of Oakland Pia Franzese (510)627-1154   pfranzese@portoakland
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$5,000 $0 $5,000
Ports Inf, Sec, & AQ
$1,855 $0 $1,855
Non-bond Funding
Private***
$85,050 $0 $85,050
 
Total**** $91,905 $0 $91,905

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$105 $0 $105 $0 $0 $105
Design(PS&E)
$2,000 $0 $2,000 $0 $0 $2,000
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$89,800 $0 $89,800 $0 $0 $89,800
 
Total* $91,905 $0 $91,905 $0 $0 $91,905

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/20/2014 

10/08/2015 
 

 
10/20/2014 

10/08/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2016 

07/31/2016 
 

 
03/01/2016 

07/31/2016 
100   

07/31/2016 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2016 

10/01/2017 
 

 
08/01/2016 

10/01/2017 
100   

05/01/2018 


-7 
Begin Closeout Phase

End Closeout Phase
07/01/2017 

10/01/2017 
 

 
07/01/2017 

10/01/2017 
 

06/01/2018 


-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 11,200 lf
Nbr of Facilities Modified 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.