San Elijo Lagoon Double Track

Description: Install 1.5 miles of new double track, replace bridge 240.4 at CP Cardiff, reconfigure Chesterfield Avenue grade crossing, and install new signals.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Diego
City Encinitas, Solana Beach
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  1.5 mile      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SANDAG Bruce Smith (619) 699-1907   bruce.smith@sandag.org
Design (PS&E) Phase
SANDAG Bruce Smith (619) 699-1907   bruce.smith@sandag.org
Right of Way Phase
SANDAG Bruce Smith (619) 699-1907   bruce.smith@sandag.org
Construction Phase
Caltrans Bruce Smith (619) 699-1907   bruce.smith@sandag.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$4,343 $0 $4,343
Non-bond Funding
State/Federal*
$9,412 $0 $9,412
Local**
$56,499 $0 $56,499
 
Total**** $70,254 $0 $70,254

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,378 $0 $1,378 $0 $0 $1,378
Design(PS&E)
$7,669 $0 $7,669 $0 $0 $7,669
Right of Way
$1,585 $0 $1,585 $0 $0 $1,585
Construction
$59,622 $0 $59,622 $0 $0 $59,622
 
Total* $70,254 $0 $70,254 $0 $0 $70,254

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/08/2011 

08/31/2013 
 

 
03/08/2011 

08/31/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/11/2013 

03/02/2016 
 

 
10/11/2013 

03/02/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
06/01/2012 

04/30/2016 
 

 
06/01/2012 

04/30/2016 
100   

 


Begin Construction Phase

End Construction Phase
09/16/2016 

09/16/2018 
 

 
09/16/2016 

09/16/2018 
94   

09/30/2018 


Begin Closeout Phase

End Closeout Phase
09/17/2018 

09/17/2023 
 

 
09/17/2018 

09/17/2023 
 

09/30/2023 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 1.5 mile

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.