Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Monte Vista Grade Separation at UPRR Line |
Description: Construct grade separation at Monte Vista Avenue
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino |
City | Montclair |
Zip Code | 91763 |
Senate District |
20 |
Assembly District | 52 |
Congressional District | 35 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Montclair | Brian Smith | (909) 884-8276 | bsmith@sandbag.ca.gov | |
Design (PS&E) Phase |
City of Montclair | Brian Smith | (909) 884-8276 | bsmith@sandbag.ca.gov | |
Right of Way Phase |
City of Montclair | Brian Smith | (909) 884-8276 | bsmith@sandbag.ca.gov | |
Construction Phase |
SANBAG | Brian Smith | (909) 884-8276 | bsmith@sandbag.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$2,113 | $-1,094 | $1,019 | ||||
LSR |
$1,842 | $-1,165 | $677 | ||||
Non-bond Funding | |||||||
State/Federal* |
$12,152 | $8,538 | $20,690 | ||||
Local** |
$6,646 | $-4,893 | $1,753 | ||||
Total**** | $22,753 | $1,386 | $24,139 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$22,753 | $1,386 | $24,139 | $22,287 | $22,287 | $1,852 | |
Total* | $22,753 | $1,386 | $24,139 | $22,287 | $22,287 | $1,852 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/01/2002 07/19/2013 |
|
04/01/2002 07/19/2013 |
100 | 04/01/2002 07/19/2013 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2003 03/01/2016 |
|
01/01/2003 03/01/2016 |
100 | 01/01/2003 03/01/2016 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2003 03/01/2016 |
08/17/2016 |
01/01/2003 04/27/2016 |
100 | 01/01/2003 03/01/2016 |
0 2 |
Begin Construction Phase
End Construction Phase |
11/02/2016 01/31/2019 |
08/17/2016 08/17/2016 |
02/07/2017 05/01/2019 |
100 | 09/05/2017 02/18/2020 |
-7 -10 |
Begin Closeout Phase
End Closeout Phase |
02/02/2019 08/01/2019 |
08/17/2016 |
05/02/2019 03/05/2020 |
0 | 06/17/2020 01/23/2023 |
-14 -35 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.