Monte Vista Grade Separation at UPRR Line

Description: Construct grade separation at Monte Vista Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino
City Montclair
Zip Code 91763
 
Senate District
20
Assembly District 52
Congressional District 35
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Montclair Brian Smith (909) 884-8276   bsmith@sandbag.ca.gov
Design (PS&E) Phase
City of Montclair Brian Smith (909) 884-8276   bsmith@sandbag.ca.gov
Right of Way Phase
City of Montclair Brian Smith (909) 884-8276   bsmith@sandbag.ca.gov
Construction Phase
SANBAG Brian Smith (909) 884-8276   bsmith@sandbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$2,113 $-1,094 $1,019
LSR
$1,842 $-1,165 $677
Non-bond Funding
State/Federal*
$12,152 $8,538 $20,690
Local**
$6,646 $-4,893 $1,753
 
Total**** $22,753 $1,386 $24,139

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$22,753 $1,386 $24,139 $22,287 $22,287 $1,852
 
Total* $22,753 $1,386 $24,139 $22,287 $22,287 $1,852

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2002 

07/19/2013 
 

 
04/01/2002 

07/19/2013 
100  04/01/2002 

07/19/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2003 

03/01/2016 
 

 
01/01/2003 

03/01/2016 
100  01/01/2003 

03/01/2016 


Begin Right of Way Phase

End Right of Way Phase
01/01/2003 

03/01/2016 
 

08/17/2016 
01/01/2003 

04/27/2016 
100  01/01/2003 

03/01/2016 


Begin Construction Phase

End Construction Phase
11/02/2016 

01/31/2019 
08/17/2016 

08/17/2016 
02/07/2017 

05/01/2019 
100  09/05/2017 

02/18/2020 
-7 

-10 
Begin Closeout Phase

End Closeout Phase
02/02/2019 

08/01/2019 
08/17/2016 

 
05/02/2019 

03/05/2020 
06/17/2020 

01/23/2023 
-14 

-35 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.