Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Middle Harbor Terminal Redeveloment |
Description: Add rail trackage, add truck gate lanes and associated scales and security infrastructure.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Long Beach |
Zip Code | |
Senate District |
33 |
Assembly District | 70 |
Congressional District | 47 |
Caltrans District |
07 |
County/State Route | Los Angeles N/A |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 3 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Long Beach | Allison Yoh | 562-283-7175 | allison.yoh@polb.com | |
Design (PS&E) Phase |
Port of Long Beach | Allison Yoh | 562-283-7175 | allison.yoh@polb.com | |
Right of Way Phase |
Port of Long Beach | Allison Yoh | 562-283-7175 | allison.yoh@polb.com | |
Construction Phase |
Port of Long Beach | Allison Yoh | 562-283-7175 | allison.yoh@polb.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$12,600 | $2,836 | $15,436 | ||||
Non-bond Funding | |||||||
Local** |
$140,919 | $0 | $140,919 | ||||
Total**** | $153,519 | $2,836 | $156,355 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$153,519 | $2,836 | $156,355 | $0 | $0 | $156,355 | |
Total* | $153,519 | $2,836 | $156,355 | $0 | $0 | $156,355 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2005 03/31/2010 |
05/17/2017 05/17/2017 |
01/01/2005 03/31/2010 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2015 07/01/2017 |
05/17/2017 05/17/2017 |
03/01/2015 07/01/2017 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2017 09/30/2020 |
05/17/2017 05/17/2017 |
12/01/2017 09/30/2020 |
74 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/30/2020 11/30/2020 |
05/17/2017 |
09/30/2020 11/30/2020 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 3 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.