Caltrans Logo

Middle Harbor Terminal Redeveloment

Description: Add rail trackage, add truck gate lanes and associated scales and security infrastructure.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Long Beach
Zip Code
 
Senate District
33
Assembly District 70
Congressional District 47
 
Caltrans District
07
 
 
County/State Route Los Angeles N/A
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  3      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Long Beach Allison Yoh 562-283-7175   allison.yoh@polb.com
Design (PS&E) Phase
Port of Long Beach Allison Yoh 562-283-7175   allison.yoh@polb.com
Right of Way Phase
Port of Long Beach Allison Yoh 562-283-7175   allison.yoh@polb.com
Construction Phase
Port of Long Beach Allison Yoh 562-283-7175   allison.yoh@polb.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$12,600 $2,836 $15,436
Non-bond Funding
Local**
$140,919 $0 $140,919
 
Total**** $153,519 $2,836 $156,355

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$153,519 $2,836 $156,355 $0 $0 $156,355
 
Total* $153,519 $2,836 $156,355 $0 $0 $156,355

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2005 

03/31/2010 
05/17/2017 

05/17/2017 
01/01/2005 

03/31/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2015 

07/01/2017 
05/17/2017 

05/17/2017 
03/01/2015 

07/01/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2017 

09/30/2020 
05/17/2017 

05/17/2017 
12/01/2017 

09/30/2020 
74   

 


Begin Closeout Phase

End Closeout Phase
09/30/2020 

11/30/2020 
05/17/2017 

 
09/30/2020 

11/30/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 3

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.