Caltrans Logo

I-405 HOV Lane

Description: I-405 improvement project for Orange County and Southern California region.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Orange
City
Zip Code
 
Senate District
34
Assembly District 72, 74
Congressional District 48
 
Caltrans District
12
 
 
County/State Route Orange 405
Postmile Begin/End 9.3 24.2
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Orange County Transportation Authority Jeff Mills (714)560-5925   jmills1@octa.net
Design (PS&E) Phase
Orange County Transportation Authority Jeff Mills (714)560-5925   jmills1@octa.net
Right of Way Phase
Orange County Transportation Authority Jeff Mills (714)560-5925   jmills1@octa.net
Construction Phase
Orange County Transportation Authority Jeff Mills (714)560-5925   jmills1@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$7,771 $0 $7,771
Non-bond Funding
State/Federal*
$125,528 $0 $125,528
Local**
$1,184,308 $0 $1,184,308
Private***
$188,529 $0 $188,529
 
Total**** $1,506,136 $0 $1,506,136

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$84,662 $0 $84,662 $16,303 $84,662 $0
Design(PS&E)
$269,052 $0 $269,052 $45,416 $269,052 $0
Right of Way
$298,651 $0 $298,651 $112,344 $298,651 $0
Construction
$853,771 $0 $853,771 $1,287,846 $853,771 $0
 
Total* $1,506,136 $0 $1,506,136 $1,461,910 $1,506,136 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/31/2009 

05/31/2015 
 

 
03/31/2009 

05/31/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/2014 

11/30/2015 
12/07/2016 

12/07/2016 
10/30/2014 

11/30/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
09/30/2015 

04/30/2020 
12/07/2016 

12/07/2016 
09/30/2015 

04/30/2020 
100   

12/10/2021 


-20 
Begin Construction Phase

End Construction Phase
01/31/2017 

08/31/2026 
12/07/2016 

12/07/2016 
01/31/2017 

08/31/2026 
96   

02/28/2024 


31 
Begin Closeout Phase

End Closeout Phase
09/01/2026 

08/31/2027 
12/07/2016 

 
09/01/2026 

08/31/2027 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.