US-101 Marin Sonoma Narrows HOV Lane Project Phase 2 |
Description: Improve freight throughput and reduce congestion by adding HOV lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Marin, Sonoma |
City | Novato, Petaluma |
Zip Code | |
Senate District |
02 |
Assembly District | 10 |
Congressional District | 02 |
Caltrans District |
04 |
County/State Route | Marin 101 |
Postmile Begin/End | 0 27.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Sonoma County Transportation Authority | James Cameron | 707-565-5377 | james.cameron@scta.ca.gov | |
Design (PS&E) Phase |
Sonoma County Transportation Authority | James Cameron | 707-565-5377 | james.cameron@scta.ca.gov | |
Right of Way Phase |
Sonoma County Transportation Authority | James Cameron | 707-565-5377 | james.cameron@scta.ca.gov | |
Construction Phase |
Sonoma County Transportation Authority | James Cameron | 707-565-5377 | james.cameron@scta.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$3,000 | $0 | $3,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$18,462 | $0 | $18,462 | ||||
Local** |
$16,200 | $0 | $16,200 | ||||
Total**** | $37,662 | $0 | $37,662 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$2,642 | $0 | $2,642 | $0 | $0 | $2,642 | |
Right of Way |
$20 | $0 | $20 | $0 | $0 | $20 | |
Construction |
$35,000 | $0 | $35,000 | $0 | $0 | $35,000 | |
Total* | $37,662 | $0 | $37,662 | $0 | $0 | $37,662 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/23/2001 10/29/2009 |
|
04/23/2001 10/29/2009 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/08/2013 08/11/2017 |
|
08/08/2013 08/11/2017 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/08/2013 08/11/2017 |
|
08/08/2013 08/11/2017 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/30/2017 12/31/2019 |
08/16/2017 |
03/06/2018 12/31/2019 |
90 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2020 12/30/2020 |
|
01/01/2020 12/30/2020 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.