I-80/SR-65 Interchange Phase I-Third Lane Project

Description: Construct third lane for 1.3 miles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Rocklin, Roseville
Zip Code
 
Senate District
04
Assembly District 06
Congressional District 04
 
Caltrans District
03
 
 
County/State Route Placer 65
Postmile Begin/End 5 6.6
Project Benefits
 Benefit Baseline Actual
New Interchanges (Nbr Constructed)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Placer County Transportation Planning Agency Rodney Murphy (530)741-5127   rodney.murphy@dot.ca.gov
Design (PS&E) Phase
Caltrans Rodney Murphy (530)741-5127   rodney.murphy@dot.ca.gov
Right of Way Phase
Caltrans Rodney Murphy (530)741-5127   rodney.murphy@dot.ca.gov
Construction Phase
Caltrans Rodney Murphy (530)741-5127   rodney.murphy@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$3,600 $0 $3,600
SHOPP Augmentation
$0 $199 $199
Non-bond Funding
State/Federal*
$7,950 $23,393 $31,343
Local**
$350 $7,561 $7,911
 
Total**** $11,900 $31,153 $43,053

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$11,900 $31,153 $43,053 $41,540 $0 $43,053
 
Total* $11,900 $31,153 $43,053 $41,540 $0 $43,053

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/10/2015 

09/08/2016 
 

 
07/10/2015 

09/08/2016 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/09/2016 

06/26/2017 
 

 
09/09/2016 

06/26/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
09/09/2016 

06/26/2017 
 

 
09/09/2016 

06/26/2017 
100   

 


Begin Construction Phase

End Construction Phase
11/14/2017 

11/01/2020 
 

 
11/14/2017 

11/01/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2022 

12/01/2023 
 

 
11/01/2022 

12/01/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
New Interchanges (Nbr Constructed) 1

Bond Funding Cost
Adopted:
$3,600,000
Current Approved:
$3,600,000
Actual Expenditures:
$3,472,000

 

Status as of December 31, 2023.