SR99 Auxiliary Lanes Project

Description: In Sacramento County from I-5 Connector to West Elkhorn Blvd Overcrossing, construct auxiliary lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Sacramento
City Sacramento
Zip Code
 
Senate District
06
Assembly District 07
Congressional District 06
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End 32.5 33.5
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Nadarajah Suthahar 530-741-4008   sutha.suthahar@dot.ca.gov
Design (PS&E) Phase
Caltrans Nadarajah Suthahar 530-741-4008   sutha.suthahar@dot.ca.gov
Right of Way Phase
Caltrans Nadarajah Suthahar 530-741-4008   sutha.suthahar@dot.ca.gov
Construction Phase
Caltrans Nadarajah Suthahar 530-741-4008   sutha.suthahar@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$5,295 $0 $5,295
TCIF
$900 $0 $900
Non-bond Funding
Local**
$900 $0 $900
 
Total**** $7,095 $0 $7,095

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$170 $0 $170 $0 $0 $170
Design(PS&E)
$600 $0 $600 $0 $0 $600
Right of Way
$25 $0 $25 $0 $0 $25
Construction
$6,300 $0 $6,300 $0 $0 $6,300
 
Total* $7,095 $0 $7,095 $0 $0 $7,095

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2017 

02/14/2018 
 

 
12/01/2017 

02/14/2018 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/15/2017 

04/23/2018 
 

 
12/15/2017 

04/23/2018 
100   

 


Begin Right of Way Phase

End Right of Way Phase
12/15/2017 

04/23/2018 
 

 
12/15/2017 

04/23/2018 
100   

 


Begin Construction Phase

End Construction Phase
08/20/2018 

12/01/2019 
 

 
08/20/2018 

12/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2019 

12/01/2023 
 

 
12/01/2019 

12/01/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.