SR99 Auxiliary Lanes Project |
Description: In Sacramento County from I-5 Connector to West Elkhorn Blvd Overcrossing, construct auxiliary lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | |
Senate District |
06 |
Assembly District | 07 |
Congressional District | 06 |
Caltrans District |
03 |
County/State Route | Sacramento 99 |
Postmile Begin/End | 32.5 33.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Nadarajah Suthahar | 530-741-4008 | sutha.suthahar@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Nadarajah Suthahar | 530-741-4008 | sutha.suthahar@dot.ca.gov | |
Right of Way Phase |
Caltrans | Nadarajah Suthahar | 530-741-4008 | sutha.suthahar@dot.ca.gov | |
Construction Phase |
Caltrans | Nadarajah Suthahar | 530-741-4008 | sutha.suthahar@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$5,295 | $0 | $5,295 | ||||
TCIF |
$900 | $0 | $900 | ||||
Non-bond Funding | |||||||
Local** |
$900 | $0 | $900 | ||||
Total**** | $7,095 | $0 | $7,095 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$170 | $0 | $170 | $0 | $0 | $170 | |
Design(PS&E) |
$600 | $0 | $600 | $0 | $0 | $600 | |
Right of Way |
$25 | $0 | $25 | $0 | $0 | $25 | |
Construction |
$6,300 | $0 | $6,300 | $0 | $0 | $6,300 | |
Total* | $7,095 | $0 | $7,095 | $0 | $0 | $7,095 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/01/2017 02/14/2018 |
|
12/01/2017 02/14/2018 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/15/2017 04/23/2018 |
|
12/15/2017 04/23/2018 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/15/2017 04/23/2018 |
|
12/15/2017 04/23/2018 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/20/2018 12/01/2019 |
|
08/20/2018 12/01/2019 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/01/2019 12/01/2023 |
|
12/01/2019 12/01/2023 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.