SR-60 Archilabd Ave Interchange Improvement |
Description: Modify and Improve interchanges
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino |
City | |
Zip Code | |
Senate District |
20 |
Assembly District | 52 |
Congressional District | 35 |
Caltrans District |
08 |
County/State Route | San Bernardino 60 |
Postmile Begin/End | 7.8 7.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Roadway Modification (Lane Miles Modified) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
San Bernardino County Transportation Authority | Andrea Nieto | 909-884-8276 | aneito@gosbcta.com | |
Design (PS&E) Phase |
San Bernardino County Transportation Authority | Andrea Nieto | 909-884-8276 | aneito@gosbcta.com | |
Right of Way Phase |
San Bernardino County Transportation Authority | Andrea Nieto | 909-884-8276 | aneito@gosbcta.com | |
Construction Phase |
San Bernardino County Transportation Authority | Andrea Nieto | 909-884-8276 | aneito@gosbcta.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$1,310 | $0 | $1,310 | ||||
Non-bond Funding | |||||||
Local** |
$15,906 | $0 | $15,906 | ||||
Total**** | $17,216 | $0 | $17,216 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$867 | $0 | $867 | $0 | $0 | $867 | |
Design(PS&E) |
$1,098 | $0 | $1,098 | $0 | $0 | $1,098 | |
Right of Way |
$1,458 | $0 | $1,458 | $0 | $0 | $1,458 | |
Construction |
$13,793 | $0 | $13,793 | $0 | $0 | $13,793 | |
Total* | $17,216 | $0 | $17,216 | $0 | $0 | $17,216 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/22/2016 03/08/2018 |
|
08/22/2016 03/08/2018 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/09/2018 05/31/2019 |
|
03/09/2018 05/31/2019 |
40 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/11/2018 05/31/2019 |
|
07/11/2018 05/31/2019 |
40 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/28/2019 03/01/2021 |
|
10/28/2019 03/01/2021 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/02/2021 12/31/2021 |
|
03/02/2021 12/31/2021 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Roadway Modification (Lane Miles Modified) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.