Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
I-5 Improvement from SR-73 to Oso Parkway (Segment 1) |
Description: Modify and Improve Interchanges
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Orange |
City | |
Zip Code | |
Senate District |
36, 37 |
Assembly District | 68, 73 |
Congressional District | 45, 48, 49 |
Caltrans District |
12 |
County/State Route | Orange 5 |
Postmile Begin/End | 12.4 14.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Orange County Transportation Authority | Hamid Torkamanha | (714)560-5436 | htorkamanha@octa.net | |
Design (PS&E) Phase |
Orange County Transportation Authority | Hamid Torkamanha | (714)560-5436 | htorkamanha@octa.net | |
Right of Way Phase |
Caltrans | Hamid Torkamanha | (714)560-5436 | htorkamanha@octa.net | |
Construction Phase |
Caltrans | Hamid Torkamanha | (714)560-5436 | htorkamanha@octa.net | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$26,991 | $0 | $26,991 | ||||
Non-bond Funding | |||||||
State/Federal* |
$120,144 | $0 | $120,144 | ||||
Local** |
$32,633 | $0 | $32,633 | ||||
Total**** | $179,768 | $0 | $179,768 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,989 | $0 | $1,989 | $0 | $0 | $1,989 | |
Design(PS&E) |
$10,349 | $0 | $10,349 | $0 | $0 | $10,349 | |
Right of Way |
$34,141 | $0 | $34,141 | $0 | $0 | $34,141 | |
Construction |
$133,289 | $0 | $133,289 | $0 | $0 | $133,289 | |
Total* | $179,768 | $0 | $179,768 | $0 | $0 | $179,768 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2011 05/06/2014 |
|
10/01/2011 05/06/2014 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/03/2015 03/01/2019 |
|
03/03/2015 03/01/2019 |
55 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2016 02/01/2019 |
|
01/01/2016 02/01/2019 |
55 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2019 01/01/2024 |
|
10/01/2019 01/01/2024 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/01/2024 01/01/2031 |
|
02/01/2024 01/01/2031 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.