Caltrans Logo

I-5 Improvement from SR-73 to Oso Parkway (Segment 1)

Description: Modify and Improve Interchanges

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Orange
City
Zip Code
 
Senate District
36, 37
Assembly District 68, 73
Congressional District 45, 48, 49
 
Caltrans District
12
 
 
County/State Route Orange 5
Postmile Begin/End 12.4 14.5
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Orange County Transportation Authority Hamid Torkamanha (714)560-5436   htorkamanha@octa.net
Design (PS&E) Phase
Orange County Transportation Authority Hamid Torkamanha (714)560-5436   htorkamanha@octa.net
Right of Way Phase
Caltrans Hamid Torkamanha (714)560-5436   htorkamanha@octa.net
Construction Phase
Caltrans Hamid Torkamanha (714)560-5436   htorkamanha@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$26,991 $0 $26,991
Non-bond Funding
State/Federal*
$120,144 $0 $120,144
Local**
$32,633 $0 $32,633
 
Total**** $179,768 $0 $179,768

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,989 $0 $1,989 $0 $0 $1,989
Design(PS&E)
$10,349 $0 $10,349 $0 $0 $10,349
Right of Way
$34,141 $0 $34,141 $0 $0 $34,141
Construction
$133,289 $0 $133,289 $0 $0 $133,289
 
Total* $179,768 $0 $179,768 $0 $0 $179,768

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2011 

05/06/2014 
 

 
10/01/2011 

05/06/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/03/2015 

03/01/2019 
 

 
03/03/2015 

03/01/2019 
55   

 


Begin Right of Way Phase

End Right of Way Phase
01/01/2016 

02/01/2019 
 

 
01/01/2016 

02/01/2019 
55   

 


Begin Construction Phase

End Construction Phase
10/01/2019 

01/01/2024 
 

 
10/01/2019 

01/01/2024 
 

 


Begin Closeout Phase

End Closeout Phase
02/01/2024 

01/01/2031 
 

 
02/01/2024 

01/01/2031 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.