Caltrans Logo

Bus Purchase

Description: Purchase 2 new gasoline buses to replace existing buses that are past their useful life.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Colusa
City Colusa
Zip Code 95932
 
Senate District
04
Assembly District 03
Congressional District 03
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    10  
Increased Ridership  10    10  
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  20    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE AZEVEDO (530) 458-0471   MAZEVEDO@COUNTYOFCOLUSA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $56 $56
PTMISEA-99313
$0 $134 $134
PTMISEA-99314
$0 $0 $0
Non-bond Funding
 
Total**** $0 $190 $190

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $190 $190 $190 $190 $0
 
Total* $0 $190 $190 $190 $190 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/29/2023 

06/15/2023 
 

 
05/29/2023 

06/15/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
06/25/2023 

06/30/2023 
 

 
06/25/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 10
Increased Ridership 10 10
Reduced Emissions 10
Reduced Operating/Maintenance Cost 20 5

Bond Funding Cost
Adopted:
$0
Current Approved:
$134,030
Actual Expenditures:
$134,030

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31