BART Station Wayfinding, Lighting, Hardscape & Cleanliness Improvements |
Description: Provide wayfinding signage and real-time display at BART Stations and station sites for improved visibility and patron safety etc.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda, Contra Costa, San Francisco |
City | Oakland |
Zip Code | 94612 |
Senate District |
13, 16 |
Assembly District | 03, 09 |
Congressional District | 07, 08, 09, 10, 11, 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
TIAN FENG | (510) 464-6549 | TFENG@BART.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $129 | $129 | ||||
PTMISEA-99313 |
$4,605 | $-203 | $4,402 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $7,384 | $7,384 | ||||
Local** |
$1,151 | $33,160 | $34,311 | ||||
Total**** | $5,756 | $40,471 | $46,227 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$5,756 | $40,471 | $46,227 | $37,211 | $37,211 | $9,015 | |
Total* | $5,756 | $40,471 | $46,227 | $37,211 | $37,211 | $9,015 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2014 08/31/2015 |
|
12/01/2014 08/31/2015 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2015 12/31/2016 |
03/14/2023 |
09/01/2015 12/31/2022 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/31/2017 07/31/2017 |
03/14/2023 03/14/2023 |
01/31/2023 06/30/2024 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31