Caltrans Logo

BART Station Wayfinding, Lighting, Hardscape & Cleanliness Improvements

Description: Provide wayfinding signage and real-time display at BART Stations and station sites for improved visibility and patron safety etc.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda, Contra Costa, San Francisco
City Oakland
Zip Code 94612
 
Senate District
13, 16
Assembly District 03, 09
Congressional District 07, 08, 09, 10, 11, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TIAN FENG (510) 464-6549   TFENG@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $129 $129
PTMISEA-99313
$4,605 $-203 $4,402
Non-bond Funding
State/Federal*
$0 $7,384 $7,384
Local**
$1,151 $33,160 $34,311
 
Total**** $5,756 $40,471 $46,227

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,756 $40,471 $46,227 $37,211 $37,211 $9,015
 
Total* $5,756 $40,471 $46,227 $37,211 $37,211 $9,015

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2014 

08/31/2015 
 

 
12/01/2014 

08/31/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2015 

12/31/2016 
 

03/14/2023 
09/01/2015 

12/31/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
01/31/2017 

07/31/2017 
03/14/2023 

03/14/2023 
01/31/2023 

06/30/2024 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31