Caltrans Logo

Escalon's Bus Replacement

Description: The City of Escalon eTrans service intends to purchase a replacement for it's bus #1

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 26
Congressional District 10
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      25  
Reduced Emissions      10  
Reduced Operating/Maintenance Cost  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RYAN NIBLOCK (209) 235-0588   NIBLOCK@SJCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $20 $20
PTMISEA-99313
$100 $-32 $68
Non-bond Funding
 
Total**** $100 $-12 $88

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$100 $-12 $88 $68 $68 $20
 
Total* $100 $-12 $88 $68 $68 $20

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2015 

06/30/2015 
 

 
03/01/2015 

06/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
02/28/2016 

06/30/2016 
05/19/2020 

05/19/2020 
06/01/2020 

06/30/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25
Reduced Emissions 10
Reduced Operating/Maintenance Cost 25

Bond Funding Cost
Adopted:
$100,000
Current Approved:
$67,862
Actual Expenditures:
$67,862

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31