Manteca Transit Center Audio/Visual Upgrades Project

Description: Upgrading the audio/visual system in Mantyeca's transit center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 12
Congressional District 09
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    5  
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RYAN NIBLOCK (209) 235-0588   NIBLOCK@SJCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$35 $-35 $0
PTMISEA-99313
$149 $-8 $141
Non-bond Funding
 
Total**** $184 $-43 $141

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$184 $-43 $141 $141 $141 $0
 
Total* $184 $-43 $141 $141 $141 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2021 

03/31/2022 
 

03/29/2022 
03/01/2021 

12/31/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2022 

06/30/2022 
03/29/2022 

03/29/2022 
01/01/2022 

01/31/2022 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 5
Increased Ridership 5

Bond Funding Cost
Adopted:
$183,623
Current Approved:
$140,965
Actual Expenditures:
$140,965

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31