Office Enhancement & ADA Project

Description: Replace main door and provide ADA access to the Para Transit Office Facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Humboldt
City Fortuna
Zip Code 95540
 
Senate District
02
Assembly District 02
Congressional District 02
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      50  
Reduced Operating/Maintenance Cost  5    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KEVIN CARTER (707) 725-1472   KCARTER@CI.FORTUNA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$70 $44 $114
PTMISEA-99314
$1 $0 $1
Non-bond Funding
Local**
$0 $9 $9
 
Total**** $71 $52 $124

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$15 $0 $15 $1 $1 $14
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$56 $52 $109 $123 $123 $-14
 
Total* $71 $52 $124 $124 $124 $-1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2015 

 
 

 
10/01/2015 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2015 

03/30/2016 
 

 
12/01/2015 

03/30/2016 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2016 

05/01/2016 
 

 
04/01/2016 

05/01/2016 
 

 


Begin Closeout Phase

End Closeout Phase
08/30/2016 

10/15/2016 
 

 
08/30/2017 

10/15/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50
Reduced Operating/Maintenance Cost 5 10

Bond Funding Cost
Adopted:
$71,309
Current Approved:
$115,539
Actual Expenditures:
$115,539

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31