FY 14/15 Bus Shelters

Description: Purchas and installation of bus shelters

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 31
Congressional District 04, 16
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      2  
Increased Ridership  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JEFF FINDLEY (559) 675-0721   JEFF@MADERA@CTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $10 $10
PTMISEA-99313
$100 $43 $143
Non-bond Funding
 
Total**** $100 $52 $152

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$100 $52 $152 $152 $152 $0
 
Total* $100 $52 $152 $152 $152 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

11/01/2017 
02/16/2022 

02/16/2022 
09/01/2021 

05/01/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
12/31/2017 

01/31/2018 
02/16/2022 

02/16/2022 
05/31/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2
Increased Ridership 1

Bond Funding Cost
Adopted:
$100,000
Current Approved:
$142,677
Actual Expenditures:
$142,677

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31