Caltrans Logo

SMOOTH Van Purchase

Description: Purchase an ADA Compliant Ford Transit 8 passenger gas van for CTSA for the Santa Maria Valley area.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Santa Maria
Zip Code 93110
 
Senate District
35
Assembly District 19
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  20    30  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$51 $0 $51
Non-bond Funding
State/Federal*
$0 $0 $0
 
Total**** $51 $0 $51

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$51 $0 $51 $125 $125 $-74
 
Total* $51 $0 $51 $125 $125 $-74

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2017 

12/01/2017 
 

 
11/01/2017 

12/01/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2018 

01/30/2018 
 

 
03/01/2018 

03/30/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 20 30

Bond Funding Cost
Adopted:
$50,797
Current Approved:
$50,797
Actual Expenditures:
$50,797

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31