2017 Purchase 4 CNG Vehicles

Description: Purchase up to 5 CNG powered, ADA-compliant replacement transit vehicles. Two vehicles will be medium-size, medium-duty, three vehicles will be paratransit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Redondo Beach
Zip Code 90277
 
Senate District
26
Assembly District 66
Congressional District 33
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  8    8  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOYCE ROONEY (310) 318-0610   JOYCE.ROONEY@REDONDO.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99314
$30 $0 $30
Non-bond Funding
State/Federal*
$120 $468 $588
Local**
$0 $115 $115
 
Total**** $150 $585 $735

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$150 $585 $735 $735 $735 $0
 
Total* $150 $585 $735 $735 $735 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/30/2017 

12/30/2018 
 

 
11/30/2017 

12/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
03/30/2018 

06/30/2019 
04/24/2020 

03/03/2020 
09/30/2019 

12/31/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 8 8

Bond Funding Cost
Adopted:
$30,000
Current Approved:
$30,000
Actual Expenditures:
$30,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31