Purchase 8 CNG Mini-Buses

Description: Funding will go towards the purchase of eight CNG mini-buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92502
 
Senate District
31
Assembly District 61
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  22      
Reduced Operating/Maintenance Cost      14  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RONALD PROFETA (951) 787-7989   RPROFETA@RIVERSIDE.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$13 $0 $13
Non-bond Funding
State/Federal*
$0 $512 $512
 
Total**** $13 $513 $526

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$13 $513 $526 $526 $526 $0
 
Total* $13 $513 $526 $526 $526 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
09/10/2020 

09/10/2020 
04/26/2019 

05/01/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
09/10/2020 

09/10/2020 
05/01/2020 

06/30/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 22
Reduced Operating/Maintenance Cost 14

Bond Funding Cost
Adopted:
$12,976
Current Approved:
$12,976
Actual Expenditures:
$12,976

 

Status as of June 30, 2024.