Gateway (Valley View Grade Separation) |
Description: Construct Underpass
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Santa Fe Springs |
Zip Code | |
Senate District |
30 |
Assembly District | 56 |
Congressional District | 38 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
City of Santa Fe Springs | Donald Jensen | 562-868-0511 | donjensen@santafesprings.org | |
Right of Way Phase |
City of Santa Fe Springs | Sarina Morales Choate | 562-868-0511 | sarinamoraleschoate@santafesprings.org | |
Construction Phase |
City of Santa Fe Springs | Sarina Morales Choate | 562-868-0511 | sarinamoraleschoate@santafesprings.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$25,570 | $-7,558 | $18,012 | ||||
Non-bond Funding | |||||||
State/Federal* |
$45,987 | $-3,622 | $42,365 | ||||
Local** |
$3,620 | $0 | $3,620 | ||||
Total**** | $75,177 | $-11,180 | $63,997 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$2,996 | $1,004 | $4,000 | $4,000 | $4,000 | $0 | |
Right of Way |
$10,640 | $4,641 | $15,281 | $17,367 | $17,367 | $-2,086 | |
Construction |
$61,541 | $-16,825 | $44,716 | $42,605 | $42,605 | $2,111 | |
Total* | $75,177 | $-11,180 | $63,997 | $63,972 | $63,972 | $25 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/12/2005 09/12/2005 |
|
09/12/2005 09/12/2005 |
100 | 09/12/2005 09/12/2005 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2006 03/01/2008 |
01/20/2011 |
09/01/2005 12/31/2010 |
100 | 09/01/2005 12/31/2010 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2006 10/01/2008 |
01/20/2011 |
07/01/2006 12/31/2010 |
100 | 07/01/2006 12/31/2010 |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2009 04/01/2011 |
05/23/2012 05/23/2012 |
05/31/2012 08/31/2014 |
100 | 08/20/2012 02/12/2015 |
-3 -5 |
Begin Closeout Phase
End Closeout Phase |
04/01/2011 07/01/2011 |
05/23/2012 |
09/01/2014 11/30/2014 |
100 | 02/13/2015 02/01/2016 |
-5 -14 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$25,570,000 |
Current Approved: |
$18,012,000 |
Actual Expenditures: |
$18,012,000 |
Status as of December 31, 2023.