Caltrans Logo

Gateway (Valley View Grade Separation)

Description: Construct Underpass

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Santa Fe Springs
Zip Code
 
Senate District
30
Assembly District 56
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
City of Santa Fe Springs Donald Jensen 562-868-0511   donjensen@santafesprings.org
Right of Way Phase
City of Santa Fe Springs Sarina Morales Choate 562-868-0511   sarinamoraleschoate@santafesprings.org
Construction Phase
City of Santa Fe Springs Sarina Morales Choate 562-868-0511   sarinamoraleschoate@santafesprings.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$25,570 $-7,558 $18,012
Non-bond Funding
State/Federal*
$45,987 $-3,622 $42,365
Local**
$3,620 $0 $3,620
 
Total**** $75,177 $-11,180 $63,997

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,996 $1,004 $4,000 $4,000 $4,000 $0
Right of Way
$10,640 $4,641 $15,281 $17,367 $17,367 $-2,086
Construction
$61,541 $-16,825 $44,716 $42,605 $42,605 $2,111
 
Total* $75,177 $-11,180 $63,997 $63,972 $63,972 $25

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/12/2005 

09/12/2005 
 

 
09/12/2005 

09/12/2005 
100  09/12/2005 

09/12/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2006 

03/01/2008 
 

01/20/2011 
09/01/2005 

12/31/2010 
100  09/01/2005 

12/31/2010 


Begin Right of Way Phase

End Right of Way Phase
07/01/2006 

10/01/2008 
 

01/20/2011 
07/01/2006 

12/31/2010 
100  07/01/2006 

12/31/2010 


Begin Construction Phase

End Construction Phase
02/01/2009 

04/01/2011 
05/23/2012 

05/23/2012 
05/31/2012 

08/31/2014 
100  08/20/2012 

02/12/2015 
-3 

-5 
Begin Closeout Phase

End Closeout Phase
04/01/2011 

07/01/2011 
05/23/2012 

 
09/01/2014 

11/30/2014 
100  02/13/2015 

02/01/2016 
-5 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$25,570,000
Current Approved:
$18,012,000
Actual Expenditures:
$18,012,000

 

Status as of December 31, 2023.