Caltrans Logo

New Freight Siding Antelope Valley Line

Description: Southern California Regional Rail Authority

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City
Zip Code
 
Senate District
17
Assembly District 36, 38
Congressional District 25
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  1.3      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SCRRA Joanna Capelle (213) 247-8049   capellej@scrra.net
Design (PS&E) Phase
SCRRA Joanna Capelle (213) 247-8049   capellej@scrra.net
Right of Way Phase
 
Construction Phase
SCRRA Joanna Capelle (213) 247-8049   capellej@scrra.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$7,200 $-2,429 $4,771
Non-bond Funding
Local**
$7,500 $-1,108 $6,392
 
Total**** $14,700 $-3,537 $11,163

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,500 $-78 $1,422 $1,422 $1,422 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$13,200 $-3,459 $9,741 $9,741 $9,741 $-0
 
Total* $14,700 $-3,537 $11,163 $11,164 $11,164 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/31/2008 

01/31/2008 
 

 
01/31/2008 

01/31/2008 
100   

01/31/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2008 

04/30/2009 
 

08/12/2010 
07/30/2008 

05/20/2010 
100  12/10/2008 

06/30/2010 
-4 

-1 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2009 

12/30/2010 
08/12/2010 

08/12/2010 
08/27/2010 

03/30/2011 
100  11/04/2010 

05/18/2012 
-2 

-14 
Begin Closeout Phase

End Closeout Phase
12/30/2010 

06/30/2011 
08/12/2010 

 
03/30/2011 

06/30/2011 
100  05/18/2012 

12/14/2014 
-14 

-42 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 1.3

Bond Funding Cost
Adopted:
$7,200,000
Current Approved:
$7,200,000
Actual Expenditures:
$4,771,642

 

Status as of December 31, 2023.