Caltrans Logo

South Wilmington Grade Separation

Description: Port of Los Angeles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Wilmington
Zip Code 90744
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Los Angeles Guillermo Martinez (310) 732-3090   gmartinez@portla.org
Design (PS&E) Phase
Port of Los Angeles Guillermo Martinez (310) 732-3090   gmartinez@portla.org
Right of Way Phase
Port of Los Angeles Guillermo Martinez (310) 732-3090   gmartinez@portla.org
Construction Phase
Port of Los Angeles Guillermo Martinez (310) 732-3090   gmartinez@portla.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$17,000 $-3,241 $13,759
Ports Inf, Sec, & AQ
$2,784 $37,751 $40,535
Non-bond Funding
Local**
$53,276 $-33,988 $19,288
 
Total**** $73,060 $522 $73,582

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $520 $520 $0 $0 $520
Design(PS&E)
$4,284 $2,347 $6,631 $5,658 $5,658 $973
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$68,776 $-2,345 $66,431 $52,640 $52,640 $13,791
 
Total* $73,060 $522 $73,582 $58,298 $58,298 $15,284

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2005 

04/05/2006 
 

06/27/2012 
06/01/2005 

11/15/2011 
100  06/01/2005 

02/13/2006 


70 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

07/01/2010 
06/27/2012 

06/27/2012 
06/01/2005 

04/27/2012 
100  07/01/2007 

01/13/2012 
-25 

Begin Right of Way Phase

End Right of Way Phase
07/01/2007 

12/30/2011 
06/22/2011 

06/27/2012 
07/01/2007 

06/07/2012 
100  07/01/2007 

06/07/2012 


Begin Construction Phase

End Construction Phase
01/01/2011 

01/31/2013 
06/27/2012 

06/27/2012 
11/01/2012 

11/01/2014 
100  11/01/2012 

03/30/2015 


-5 
Begin Closeout Phase

End Closeout Phase
02/01/2013 

08/30/2013 
06/27/2012 

 
11/01/2014 

11/01/2015 
75  03/31/2015 

06/30/2024 
-5 

-105 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
$19,784,000
Current Approved:
$13,759,000
Actual Expenditures:
$12,694,450

 

Status as of December 31, 2023.