Ports Rail System Tier I (Pier F Support Yard) |
Description: Improve Storage Tracks
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Long Beach |
Zip Code | |
Senate District |
27 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 1.44 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Long Beach | Eric Shen | (562) 590-4155 | shen@polb.com | |
Design (PS&E) Phase |
Port of Long Beach | Eric Shen | (562) 590-4155 | shen@polb.com | |
Right of Way Phase |
Port of Long Beach | Eric Shen | (562) 590-4155 | shen@polb.com | |
Construction Phase |
Port of Long Beach | Eric Shen | (562) 590-4155 | shen@polb.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$10,000 | $-5,907 | $4,093 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $12,800 | $12,800 | ||||
Local** |
$14,140 | $-1,891 | $12,249 | ||||
Total**** | $24,140 | $5,002 | $29,142 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,020 | $1,960 | $2,980 | $89 | $89 | $2,891 | |
Design(PS&E) |
$2,670 | $-680 | $1,990 | $4,265 | $4,265 | $-2,275 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$20,450 | $3,722 | $24,172 | $24,776 | $24,776 | $-604 | |
Total* | $24,140 | $5,002 | $29,142 | $29,130 | $29,130 | $12 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2005 03/01/2009 |
|
10/01/2005 03/01/2009 |
100 | 08/10/2011 |
0 -30 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2009 09/01/2010 |
09/27/2012 |
04/01/2009 05/03/2012 |
100 | 05/03/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2010 03/01/2012 |
09/27/2012 09/27/2012 |
11/29/2012 05/15/2014 |
100 | 09/17/2012 06/30/2015 |
2 -14 |
Begin Closeout Phase
End Closeout Phase |
04/01/2012 06/01/2012 |
09/27/2012 |
05/16/2014 07/02/2014 |
100 | 06/30/2015 09/30/2016 |
-14 -27 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 1.44 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$10,000,000 |
Current Approved: |
$4,093,000 |
Actual Expenditures: |
$4,092,747 |
Status as of December 31, 2023.