Ports Rail System Tier I (Pier F Support Yard)

Description: Improve Storage Tracks

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Long Beach
Zip Code
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  1.44    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Long Beach Eric Shen (562) 590-4155   shen@polb.com
Design (PS&E) Phase
Port of Long Beach Eric Shen (562) 590-4155   shen@polb.com
Right of Way Phase
Port of Long Beach Eric Shen (562) 590-4155   shen@polb.com
Construction Phase
Port of Long Beach Eric Shen (562) 590-4155   shen@polb.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$10,000 $-5,907 $4,093
Non-bond Funding
State/Federal*
$0 $12,800 $12,800
Local**
$14,140 $-1,891 $12,249
 
Total**** $24,140 $5,002 $29,142

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,020 $1,960 $2,980 $89 $89 $2,891
Design(PS&E)
$2,670 $-680 $1,990 $4,265 $4,265 $-2,275
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$20,450 $3,722 $24,172 $24,776 $24,776 $-604
 
Total* $24,140 $5,002 $29,142 $29,130 $29,130 $12

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2005 

03/01/2009 
 

 
10/01/2005 

03/01/2009 
100   

08/10/2011 


-30 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2009 

09/01/2010 
 

09/27/2012 
04/01/2009 

05/03/2012 
100   

05/03/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2010 

03/01/2012 
09/27/2012 

09/27/2012 
11/29/2012 

05/15/2014 
100  09/17/2012 

06/30/2015 


-14 
Begin Closeout Phase

End Closeout Phase
04/01/2012 

06/01/2012 
09/27/2012 

 
05/16/2014 

07/02/2014 
100  06/30/2015 

09/30/2016 
-14 

-27 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 1.44 1

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$4,093,000
Actual Expenditures:
$4,092,747

 

Status as of December 31, 2023.