Outer Harbor Intermodal Terminal

Description: Construction Near Dock Intermodal Terminal

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Alameda
City Oakland
Zip Code
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Nbr Terminals Modified  2      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Oakland Eve Grossman-Bukowski (510) 627-1635   egrossman@portoakland.com
Design (PS&E) Phase
Port of Oakland Eve Grossman-Bukowski (510) 627-1635   egrossman@portoakland.com
Right of Way Phase
Port of Oakland Eve Grossman-Bukowski (510) 627-1635   egrossman@portoakland.com
Construction Phase
Port of Oakland Eve Grossman-Bukowski (510) 627-1635   egrossman@portoakland.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$131,889 $110,252 $242,141
Ports Inf, Sec, & AQ
$35,000 $-19,300 $15,700
Non-bond Funding
State/Federal*
$0 $15,000 $15,000
Local**
$75,000 $-20,500 $54,500
Private***
$0 $171,900 $171,900
 
Total**** $241,889 $257,352 $499,241

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$11,000 $-6,400 $4,600 $0 $0 $4,600
Design(PS&E)
$15,000 $28,700 $43,700 $0 $0 $43,700
Right of Way
$2,000 $-2,000 $0 $0 $0 $0
Construction
$213,889 $237,052 $450,941 $0 $0 $450,941
 
Total* $241,889 $257,352 $499,241 $0 $0 $499,241

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2002 

06/30/2009 
 

08/22/2012 
01/01/2002 

07/31/2012 
100   

07/31/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2007 

06/30/2010 
08/22/2012 

08/22/2012 
08/01/2009 

09/30/2013 
85   

07/30/2016 


-34 
Begin Right of Way Phase

End Right of Way Phase
06/30/2008 

12/01/2009 
08/22/2012 

08/22/2012 
08/01/2009 

03/31/2013 
100   

03/31/2013 


Begin Construction Phase

End Construction Phase
03/01/2011 

12/31/2013 
08/22/2012 

08/22/2012 
01/01/2010 

12/31/2019 
91  01/01/2010 

12/31/2019 


Begin Closeout Phase

End Closeout Phase
12/31/2013 

06/30/2014 
08/22/2012 

 
08/01/2015 

06/30/2020 
10/01/2014 

06/30/2020 
10 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Nbr Terminals Modified 2

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.