Outer Harbor Intermodal Terminal |
Description: Construction Near Dock Intermodal Terminal
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Alameda |
City | Oakland |
Zip Code | |
Senate District |
09 |
Assembly District | 16 |
Congressional District | 09 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr Terminals Modified | 2 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Oakland | Eve Grossman-Bukowski | (510) 627-1635 | egrossman@portoakland.com | |
Design (PS&E) Phase |
Port of Oakland | Eve Grossman-Bukowski | (510) 627-1635 | egrossman@portoakland.com | |
Right of Way Phase |
Port of Oakland | Eve Grossman-Bukowski | (510) 627-1635 | egrossman@portoakland.com | |
Construction Phase |
Port of Oakland | Eve Grossman-Bukowski | (510) 627-1635 | egrossman@portoakland.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$131,889 | $110,252 | $242,141 | ||||
Ports Inf, Sec, & AQ |
$35,000 | $-19,300 | $15,700 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $15,000 | $15,000 | ||||
Local** |
$75,000 | $-20,500 | $54,500 | ||||
Private*** |
$0 | $171,900 | $171,900 | ||||
Total**** | $241,889 | $257,352 | $499,241 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$11,000 | $-6,400 | $4,600 | $0 | $0 | $4,600 | |
Design(PS&E) |
$15,000 | $28,700 | $43,700 | $0 | $0 | $43,700 | |
Right of Way |
$2,000 | $-2,000 | $0 | $0 | $0 | $0 | |
Construction |
$213,889 | $237,052 | $450,941 | $0 | $0 | $450,941 | |
Total* | $241,889 | $257,352 | $499,241 | $0 | $0 | $499,241 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2002 06/30/2009 |
08/22/2012 |
01/01/2002 07/31/2012 |
100 | 07/31/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2007 06/30/2010 |
08/22/2012 08/22/2012 |
08/01/2009 09/30/2013 |
85 | 07/30/2016 |
0 -34 |
Begin Right of Way Phase
End Right of Way Phase |
06/30/2008 12/01/2009 |
08/22/2012 08/22/2012 |
08/01/2009 03/31/2013 |
100 | 03/31/2013 |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2011 12/31/2013 |
08/22/2012 08/22/2012 |
01/01/2010 12/31/2019 |
91 | 01/01/2010 12/31/2019 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/31/2013 06/30/2014 |
08/22/2012 |
08/01/2015 06/30/2020 |
0 | 10/01/2014 06/30/2020 |
10 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr Terminals Modified | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.