Ports Rail System Tier 1 (West Basin Rail Access Improvements

Description: Improve Operations

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Long Beach
Zip Code
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  1.5      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
POLA Cristina Sar (310) 732-3627   csar@portla.org
Design (PS&E) Phase
POLA Cristina Sar (310) 732-3627   csar@portla.org
Right of Way Phase
POLA Cristina Sar (310) 732-3627   csar@portla.org
Construction Phase
POLA Cristina Sar (310) 732-3627   csar@portla.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$51,230 $-1,089 $50,141
Non-bond Funding
State/Federal*
$0 $16,000 $16,000
Local**
$74,110 $-5,154 $68,956
 
Total**** $125,340 $9,757 $135,097

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$6 $0 $6 $0 $0 $6
Design(PS&E)
$5,141 $3,839 $8,980 $0 $0 $8,980
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$120,193 $5,918 $126,111 $0 $0 $126,111
 
Total* $125,340 $9,757 $135,097 $0 $0 $135,097

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2005 

03/01/2008 
 

 
07/01/2005 

03/01/2008 
100   

03/01/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2008 

09/01/2009 
 

12/06/2012 
04/01/2008 

03/01/2013 
100   

11/15/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
02/22/2012 

12/06/2012 
04/01/2008 

01/01/2013 
100   

03/01/2013 


-2 
Begin Construction Phase

End Construction Phase
04/01/2010 

03/01/2012 
02/22/2012 

12/06/2012 
06/01/2012 

07/01/2014 
100  05/31/2012 

09/30/2017 


-40 
Begin Closeout Phase

End Closeout Phase
04/01/2012 

03/01/2013 
12/06/2012 

 
07/01/2014 

07/01/2015 
05/30/2017 

12/31/2017 
-35 

-30 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 1.5

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.