Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Ports Rail System Tier 1 (West Basin Rail Access Improvements |
Description: Improve Operations
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | Long Beach |
Zip Code | |
Senate District |
27 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 1.5 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
POLA | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Design (PS&E) Phase |
POLA | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Right of Way Phase |
POLA | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Construction Phase |
POLA | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$51,230 | $-1,089 | $50,141 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $16,000 | $16,000 | ||||
Local** |
$74,110 | $-5,154 | $68,956 | ||||
Total**** | $125,340 | $9,757 | $135,097 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$6 | $0 | $6 | $0 | $0 | $6 | |
Design(PS&E) |
$5,141 | $3,839 | $8,980 | $0 | $0 | $8,980 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$120,193 | $5,918 | $126,111 | $0 | $0 | $126,111 | |
Total* | $125,340 | $9,757 | $135,097 | $0 | $0 | $135,097 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2005 03/01/2008 |
|
07/01/2005 03/01/2008 |
100 | 03/01/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2008 09/01/2009 |
12/06/2012 |
04/01/2008 03/01/2013 |
100 | 11/15/2012 |
0 4 |
Begin Right of Way Phase
End Right of Way Phase |
|
02/22/2012 12/06/2012 |
04/01/2008 01/01/2013 |
100 | 03/01/2013 |
0 -2 |
Begin Construction Phase
End Construction Phase |
04/01/2010 03/01/2012 |
02/22/2012 12/06/2012 |
06/01/2012 07/01/2014 |
100 | 05/31/2012 09/30/2017 |
0 -40 |
Begin Closeout Phase
End Closeout Phase |
04/01/2012 03/01/2013 |
12/06/2012 |
07/01/2014 07/01/2015 |
0 | 05/30/2017 12/31/2017 |
-35 -30 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 1.5 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.