State Route 91 (Auxiliary Lanes on Westbound State Route 91 between State Route 57 and I-5)

Description: Create Fourth Mixed Use Lane to Allieviate Congestion

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City
Zip Code
 
Senate District
33, 34
Assembly District 68, 69, 72
Congressional District 39, 46
 
Caltrans District
12
 
 
County/State Route Orange 91
Postmile Begin/End 0.9 5.5
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
OCTA Pradeep Gunaratne (714) 560-5648   pgunaratne@octa.net
Design (PS&E) Phase
OCTA Pradeep Gunaratne (714) 560-5648   pgunaratne@octa.net
Right of Way Phase
Caltrans Leo Chen (949) 223-5431   leo.chen@dot.ca.gov
Construction Phase
Caltrans Leo Chen (949) 223-5431   leo.chen@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$34,950 $-9,512 $25,438
Non-bond Funding
Local**
$38,450 $-19,620 $18,830
 
Total**** $73,400 $-29,132 $44,268

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,500 $-2,420 $1,080 $1,080 $1,080 $0
Design(PS&E)
$5,387 $-2,705 $2,682 $2,682 $2,682 $0
Right of Way
$5,113 $-3,230 $1,883 $1,883 $1,883 $0
Construction
$59,400 $-20,777 $38,623 $38,622 $38,622 $1
 
Total* $73,400 $-29,132 $44,268 $44,266 $44,266 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

04/01/2010 
08/28/2008 

03/28/2012 
07/01/2007 

06/01/2010 
100  07/01/2007 

06/01/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2009 

08/01/2012 
03/28/2012 

08/28/2008 
04/01/2010 

08/01/2012 
100  04/01/2010 

08/01/2012 


Begin Right of Way Phase

End Right of Way Phase
04/01/2010 

07/01/2012 
03/28/2012 

03/28/2008 
06/01/2010 

08/01/2012 
100  06/01/2010 

08/01/2012 


Begin Construction Phase

End Construction Phase
12/01/2012 

12/01/2015 
08/28/2008 

08/28/2008 
12/01/2012 

12/01/2015 
100  02/25/2013 

06/23/2016 
-3 

-7 
Begin Closeout Phase

End Closeout Phase
12/01/2015 

12/01/2016 
03/28/2012 

 
12/01/2015 

11/01/2016 
100  06/23/2016 

06/23/2017 
-7 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 1 1

Bond Funding Cost
Adopted:
$34,950,000
Current Approved:
$27,227,000
Actual Expenditures:
$25,438,491

 

Status as of December 31, 2023.