State College Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Fullerton
Zip Code 92831
 
Senate District
29
Assembly District 79
Congressional District 42
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fullerton Ron Bowers (714) 738-6322   Ronb@ci.fullerton.ca.us
Design (PS&E) Phase
City of Fullerton Ron Bowers (714) 738-6322   Ronb@ci.fullerton.ca.us
Right of Way Phase
OCTA Joe Toolson (714) 560-5406   jtoolson@octa.net
Construction Phase
City of Fullerton Yelena Voronel (714) 738-6852   yelenav@ci.fullerton.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$30,731 $2,069 $32,800
Non-bond Funding
State/Federal*
$7,922 $-7,922 $0
Local**
$23,430 $15,324 $38,754
 
Total**** $62,083 $9,471 $71,554

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5,315 $-5,010 $305 $139 $139 $166
Design(PS&E)
$5,315 $-1,720 $3,595 $5,524 $5,524 $-1,929
Right of Way
$14,889 $4,203 $19,092 $34,387 $34,387 $-15,295
Construction
$36,564 $11,998 $48,562 $63,349 $63,349 $-14,787
 
Total* $62,083 $9,471 $71,554 $103,399 $103,399 $-31,845

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2005 

07/01/2010 
 

04/25/2012 
04/01/2005 

04/14/2011 
100  04/01/2005 

05/25/2011 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2005 

03/01/2013 
 

 
04/01/2005 

03/01/2013 
100  07/03/2006 

05/01/2013 
-15 

-2 
Begin Right of Way Phase

End Right of Way Phase
11/01/2010 

08/01/2012 
04/25/2012 

01/08/2013 
07/25/2011 

05/01/2013 
100  07/25/2011 

05/01/2013 


Begin Construction Phase

End Construction Phase
04/01/2013 

01/01/2016 
01/08/2013 

01/08/2013 
11/01/2013 

08/01/2016 
100  02/04/2014 

03/08/2018 
-3 

-19 
Begin Closeout Phase

End Closeout Phase
01/01/2016 

01/01/2019 
01/08/2013 

 
08/01/2016 

08/01/2019 
100  07/31/2018 

07/31/2021 
-24 

-24 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$30,731,000
Current Approved:
$32,800,000
Actual Expenditures:
$32,798,369

 

Status as of December 31, 2023.