Placentia Avenue Undercrossing |
Description: Construct Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | |
Zip Code | |
Senate District |
29 |
Assembly District | 79 |
Congressional District | 42 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Placentia | Michael McConaha | (714) 993-8245 | MMcConaha@placentia.org | |
Design (PS&E) Phase |
Orange County Transportation Authority | Joel Toolson | (714) 560-5406 | jtoolson@octa.net | |
Right of Way Phase |
Orange County Transportation Authority | Joel Toolson | (714) 560-5406 | jtoolson@octa.net | |
Construction Phase |
Orange County Transportation Authority | Joel Toolson | (714) 560-5406 | jtoolson@octa.net | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$14,934 | $-5,386 | $9,548 | ||||
Non-bond Funding | |||||||
State/Federal* |
$7,500 | $10,540 | $18,040 | ||||
Local** |
$16,935 | $12,271 | $29,206 | ||||
Total**** | $39,369 | $17,425 | $56,794 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$2,000 | $-1,979 | $21 | $20 | $20 | $1 | |
Design(PS&E) |
$1,966 | $1,435 | $3,401 | $6,348 | $6,348 | $-2,947 | |
Right of Way |
$10,269 | $5,102 | $15,371 | $14,633 | $14,633 | $738 | |
Construction |
$25,134 | $12,867 | $38,001 | $43,226 | $43,226 | $-5,226 | |
Total* | $39,369 | $17,425 | $56,794 | $64,228 | $64,228 | $-7,434 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2001 05/15/2001 |
|
01/01/2001 05/15/2001 |
100 | 01/01/2001 01/01/2001 |
0 4 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 09/01/2010 |
|
01/01/2009 09/01/2010 |
100 | 01/29/2009 06/30/2010 |
-1 2 |
Begin Right of Way Phase
End Right of Way Phase |
09/01/2008 03/01/2010 |
05/11/2011 |
09/01/2008 03/01/2011 |
100 | 08/28/2008 03/16/2011 |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2010 04/01/2013 |
05/11/2011 05/11/2011 |
10/01/2011 05/01/2014 |
100 | 07/25/2011 12/18/2014 |
2 -8 |
Begin Closeout Phase
End Closeout Phase |
04/01/2013 04/01/2016 |
05/11/2011 |
05/01/2014 05/01/2017 |
100 | 12/19/2014 12/30/2017 |
-8 -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$14,934,000 |
Current Approved: |
$9,548,000 |
Actual Expenditures: |
$9,548,000 |
Status as of December 31, 2023.