Placentia Avenue Undercrossing

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City
Zip Code
 
Senate District
29
Assembly District 79
Congressional District 42
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Placentia Michael McConaha (714) 993-8245   MMcConaha@placentia.org
Design (PS&E) Phase
Orange County Transportation Authority Joel Toolson (714) 560-5406   jtoolson@octa.net
Right of Way Phase
Orange County Transportation Authority Joel Toolson (714) 560-5406   jtoolson@octa.net
Construction Phase
Orange County Transportation Authority Joel Toolson (714) 560-5406   jtoolson@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$14,934 $-5,386 $9,548
Non-bond Funding
State/Federal*
$7,500 $10,540 $18,040
Local**
$16,935 $12,271 $29,206
 
Total**** $39,369 $17,425 $56,794

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,000 $-1,979 $21 $20 $20 $1
Design(PS&E)
$1,966 $1,435 $3,401 $6,348 $6,348 $-2,947
Right of Way
$10,269 $5,102 $15,371 $14,633 $14,633 $738
Construction
$25,134 $12,867 $38,001 $43,226 $43,226 $-5,226
 
Total* $39,369 $17,425 $56,794 $64,228 $64,228 $-7,434

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2001 

05/15/2001 
 

 
01/01/2001 

05/15/2001 
100  01/01/2001 

01/01/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

09/01/2010 
 

 
01/01/2009 

09/01/2010 
100  01/29/2009 

06/30/2010 
-1 

Begin Right of Way Phase

End Right of Way Phase
09/01/2008 

03/01/2010 
 

05/11/2011 
09/01/2008 

03/01/2011 
100  08/28/2008 

03/16/2011 


Begin Construction Phase

End Construction Phase
10/01/2010 

04/01/2013 
05/11/2011 

05/11/2011 
10/01/2011 

05/01/2014 
100  07/25/2011 

12/18/2014 


-8 
Begin Closeout Phase

End Closeout Phase
04/01/2013 

04/01/2016 
05/11/2011 

 
05/01/2014 

05/01/2017 
100  12/19/2014 

12/30/2017 
-8 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$14,934,000
Current Approved:
$9,548,000
Actual Expenditures:
$9,548,000

 

Status as of December 31, 2023.