Caltrans Logo

Orangethorpe Avenue Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City
Zip Code
 
Senate District
29
Assembly District 72
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Placentia Michael McConaha (714) 993-8245   MMcConaha@placentia.org
Design (PS&E) Phase
Orange County Transportation Authority John Rawles (714) 560-5735   jrawles@octa.net
Right of Way Phase
Orange County Transportation Authority John Rawles (714) 560-5735   jrawles@octa.net
Construction Phase
Orange County Transportation Authority Ross Lew (714) 560-5775   rlew@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$41,666 $-11,342 $30,324
Non-bond Funding
Local**
$42,291 $22,710 $65,001
 
Total**** $83,957 $11,368 $95,325

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$4,557 $-3,926 $631 $631 $631 $0
Design(PS&E)
$5,241 $3,051 $8,292 $8,270 $8,270 $22
Right of Way
$21,749 $3,114 $24,863 $26,818 $26,818 $-1,955
Construction
$52,410 $9,129 $61,539 $60,915 $60,915 $624
 
Total* $83,957 $11,368 $95,325 $96,634 $96,634 $-1,309

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2001 

12/01/2008 
04/10/2008 

05/11/2011 
01/01/2001 

09/23/2009 
100  01/01/2001 

09/23/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

06/01/2013 
05/11/2011 

04/25/2012 
02/06/2009 

10/31/2011 
100  02/12/2009 

10/31/2011 


Begin Right of Way Phase

End Right of Way Phase
10/01/2010 

10/01/2012 
04/10/2008 

04/25/2012 
10/01/2010 

04/01/2012 
100  10/01/2010 

04/15/2012 


Begin Construction Phase

End Construction Phase
07/01/2013 

07/01/2016 
01/08/2013 

01/08/2013 
03/01/2013 

07/01/2016 
100  01/14/2013 

10/26/2016 


-4 
Begin Closeout Phase

End Closeout Phase
07/01/2016 

07/01/2019 
01/08/2013 

 
07/01/2016 

07/01/2019 
100  09/14/2016 

06/30/2018 
-2 

12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$41,666,000
Current Approved:
$29,700,000
Actual Expenditures:
$29,700,000

 

Status as of December 31, 2023.