Kraemer Blvd Undercrossing

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City
Zip Code
 
Senate District
29
Assembly District 72
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Placentia Michael McConaha (714) 993-8245   MMcConaha@placentia.org
Design (PS&E) Phase
Orange County Transportation Authority Bill Farthing (714) 560-5813   bfarthing@octa.net
Right of Way Phase
Orange County Transportation Authority Bill Farthing (714) 560-5813   bfarthing@octa.net
Construction Phase
Orange County Transportation Authority Bill Farthing (714) 560-5813   bfarthing@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$22,642 $-7,129 $15,513
Non-bond Funding
State/Federal*
$0 $1,460 $1,460
Local**
$23,268 $12,944 $36,212
 
Total**** $45,910 $7,275 $53,185

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,354 $-2,723 $631 $631 $631 $0
Design(PS&E)
$3,354 $1,689 $5,043 $5,561 $5,561 $-518
Right of Way
$3,260 $6,122 $9,382 $7,088 $7,088 $2,294
Construction
$35,942 $2,187 $38,129 $43,340 $43,340 $-5,210
 
Total* $45,910 $7,275 $53,185 $56,620 $56,620 $-3,435

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2001 

12/01/2008 
 

 
01/01/2001 

09/23/2009 
100  01/01/2001 

09/23/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

12/01/2010 
 

08/12/2010 
02/01/2009 

09/01/2010 
100  02/06/2009 

12/01/2010 


-3 
Begin Right of Way Phase

End Right of Way Phase
08/01/2009 

05/01/2010 
05/11/2011 

05/11/2011 
12/01/2009 

05/01/2011 
100  12/14/2009 

03/17/2011 


Begin Construction Phase

End Construction Phase
01/01/2011 

10/01/2013 
05/11/2011 

05/11/2011 
10/01/2011 

05/01/2014 
100  09/12/2011 

12/18/2014 


-8 
Begin Closeout Phase

End Closeout Phase
10/01/2013 

10/01/2016 
05/11/2011 

 
05/01/2014 

05/01/2017 
100  12/19/2014 

12/31/2017 
-8 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$22,642,000
Current Approved:
$15,513,000
Actual Expenditures:
$15,508,471

 

Status as of December 31, 2023.