Caltrans Logo

I-880 Reconstruction (29th and 23rd Avenues)

Description: Ramp Reconstruction

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Alameda
City Oakland
Zip Code
 
Senate District
09
Assembly District 16
Congressional District 09
 
Caltrans District
04
 
 
County/State Route Alameda 880
Postmile Begin/End 28.4 29.2
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  2      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Alameda County Congestion Management Agency Matt Todd (510)836-2560   MTodd@accma.ca.gov
Design (PS&E) Phase
Alameda County Congestion Management Agency Matt Todd (510)836-2560   MTodd@accma.ca.gov
Right of Way Phase
Alameda County Congestion Management Agency Matt Todd (510)836-2560   MTodd@accma.ca.gov
Construction Phase
Caltrans Stanley Gee (510) 286-4935   Stanley.Gee@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$12,000 $-10,000 $2,000
TCIF
$73,000 $0 $73,000
Non-bond Funding
State/Federal*
$1,787 $8,213 $10,000
Local**
$10,000 $2,912 $12,912
 
Total**** $96,787 $1,125 $97,912

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$4,200 $0 $4,200 $0 $0 $4,200
Design(PS&E)
$7,387 $0 $7,387 $0 $0 $7,387
Right of Way
$5,200 $1,125 $6,325 $0 $0 $6,325
Construction
$80,000 $0 $80,000 $0 $0 $80,000
 
Total* $96,787 $1,125 $97,912 $0 $0 $97,912

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2008 

04/30/2010 
 

 
04/01/2008 

04/30/2010 
100  04/01/2008 

04/30/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2009 

12/01/2011 
 

01/08/2013 
12/01/2009 

01/31/2013 
100  12/01/2009 

06/01/2013 


-4 
Begin Right of Way Phase

End Right of Way Phase
11/01/2009 

04/01/2012 
 

01/08/2013 
11/01/2009 

01/31/2013 
100  11/01/2009 

06/01/2013 


-4 
Begin Construction Phase

End Construction Phase
08/01/2012 

10/01/2015 
01/08/2013 

01/08/2013 
07/31/2013 

07/31/2017 
99  04/30/2014 

04/01/2019 
-9 

-20 
Begin Closeout Phase

End Closeout Phase
10/01/2015 

02/01/2016 
01/08/2013 

 
08/31/2017 

08/31/2018 
04/30/2019 

04/30/2020 
-20 

-20 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 2

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.