Columbia Avenue Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code
 
Senate District
31
Assembly District 64
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Design (PS&E) Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Right of Way Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Construction Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$6,000 $-1,047 $4,953
LSRCRTS
$500 $0 $500
Non-bond Funding
State/Federal*
$5,000 $0 $5,000
Local**
$22,550 $0 $22,550
 
Total**** $34,050 $-1,047 $33,003

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$143 $0 $143 $145 $145 $-2
Design(PS&E)
$1,657 $0 $1,657 $1,526 $1,526 $131
Right of Way
$6,800 $0 $6,800 $8,334 $8,334 $-1,534
Construction
$25,450 $-1,047 $24,403 $21,594 $21,594 $2,809
 
Total* $34,050 $-1,047 $33,003 $31,600 $31,600 $1,403

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2006 

04/01/2006 
 

 
01/01/2006 

04/01/2006 
100  01/01/2006 

04/05/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2006 

06/01/2008 
 

 
06/01/2006 

06/01/2008 
100  06/01/2006 

06/01/2008 


Begin Right of Way Phase

End Right of Way Phase
06/01/2006 

03/01/2008 
 

 
06/01/2006 

03/01/2008 
100  06/01/2006 

03/01/2008 


Begin Construction Phase

End Construction Phase
09/01/2008 

12/01/2009 
 

 
09/01/2008 

12/01/2009 
100  09/23/2008 

05/20/2010 
-1 

-6 
Begin Closeout Phase

End Closeout Phase
01/01/2010 

08/01/2010 
 

 
01/31/2010 

08/31/2010 
100  04/01/2012 

06/21/2012 
-26 

-22 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$6,500,000
Current Approved:
$6,000,000
Actual Expenditures:
$4,952,000

 

Status as of December 31, 2023.