Auto Center Drive Grade Separation

Description: Construct Overcrossing over Burlington Northern Sante Fe Tracks

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Corona
Zip Code 92882
 
Senate District
37
Assembly District 71
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Corona Linda Bazmi (951) 739-4960   Linda.Bazmi@ci.corona.ca.us
Design (PS&E) Phase
City of Corona Linda Bazmi (951) 739-4960   Linda.Bazmi@ci.corona.ca.us
Right of Way Phase
City of Corona Linda Bazmi (951) 739-4960   Linda.Bazmi@ci.corona.ca.us
Construction Phase
City of Corona Linda Bazmi (951) 739-4960   Linda.Bazmi@ci.corona.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$16,000 $0 $16,000
LSR
$500 $0 $500
Non-bond Funding
State/Federal*
$5,000 $675 $5,675
Local**
$10,500 $0 $10,500
 
Total**** $32,000 $675 $32,675

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$630 $0 $630 $382 $382 $248
Design(PS&E)
$1,370 $0 $1,370 $1,470 $1,470 $-100
Right of Way
$2,720 $0 $2,720 $2,724 $2,724 $-4
Construction
$27,280 $675 $27,955 $26,901 $26,901 $1,054
 
Total* $32,000 $675 $32,675 $31,478 $31,478 $1,197

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2007 

01/01/2008 
 

 
02/01/2007 

01/01/2008 
100  02/07/2007 

01/17/2008 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

09/01/2008 
 

08/10/2011 
07/01/2008 

06/30/2011 
100  06/02/2008 

06/30/2011 


Begin Right of Way Phase

End Right of Way Phase
09/01/2008 

11/01/2008 
08/12/2010 

08/10/2011 
11/01/2009 

06/30/2011 
100  11/01/2009 

06/11/2011 


Begin Construction Phase

End Construction Phase
07/01/2009 

09/01/2011 
08/12/2010 

08/12/2010 
11/01/2011 

04/30/2013 
100  05/15/2013 

09/30/2015 
-19 

-29 
Begin Closeout Phase

End Closeout Phase
09/01/2011 

10/01/2011 
08/10/2011 

 
05/01/2013 

05/01/2014 
100  10/01/2015 

10/30/2016 
-29 

-30 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$16,500,000
Current Approved:
$16,000,000
Actual Expenditures:
$16,000,000

 

Status as of December 31, 2023.