Magnolia Avenue Grade Separation (Union Pacific Railroad) |
Description: Construct Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Riverside |
Zip Code | |
Senate District |
31 |
Assembly District | 64 |
Congressional District | 44 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Design (PS&E) Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Right of Way Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Construction Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$20,000 | $-2,712 | $17,288 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,000 | $0 | $5,000 | ||||
Local** |
$27,960 | $0 | $27,960 | ||||
Total**** | $52,960 | $-2,712 | $50,248 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$160 | $0 | $160 | $628 | $628 | $-468 | |
Design(PS&E) |
$2,500 | $0 | $2,500 | $2,449 | $2,449 | $51 | |
Right of Way |
$23,500 | $0 | $23,500 | $26,522 | $26,522 | $-3,022 | |
Construction |
$26,800 | $-2,712 | $24,088 | $24,193 | $24,193 | $-105 | |
Total* | $52,960 | $-2,712 | $50,248 | $53,792 | $53,792 | $-3,544 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2006 06/01/2006 |
|
01/01/2006 06/01/2006 |
100 | 01/01/2006 06/28/2006 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 08/01/2008 |
10/15/2009 |
07/01/2007 09/01/2009 |
100 | 07/01/2006 09/24/2009 |
12 -1 |
Begin Right of Way Phase
End Right of Way Phase |
08/01/2006 02/01/2009 |
10/15/2009 |
08/01/2006 06/01/2009 |
100 | 08/01/2006 02/26/2013 |
0 -46 |
Begin Construction Phase
End Construction Phase |
03/01/2009 08/01/2010 |
10/15/2009 10/15/2009 |
02/01/2010 01/01/2012 |
100 | 12/01/2009 08/30/2012 |
2 -8 |
Begin Closeout Phase
End Closeout Phase |
08/01/2010 02/01/2011 |
|
08/30/2010 02/28/2011 |
100 | 08/30/2012 11/27/2013 |
-24 -33 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$20,000,000 |
Current Approved: |
$17,158,806 |
Actual Expenditures: |
$17,158,806 |
Status as of December 31, 2023.