Magnolia Avenue Grade Separation (Union Pacific Railroad)

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code
 
Senate District
31
Assembly District 64
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Design (PS&E) Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Right of Way Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Construction Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$20,000 $-2,712 $17,288
Non-bond Funding
State/Federal*
$5,000 $0 $5,000
Local**
$27,960 $0 $27,960
 
Total**** $52,960 $-2,712 $50,248

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$160 $0 $160 $628 $628 $-468
Design(PS&E)
$2,500 $0 $2,500 $2,449 $2,449 $51
Right of Way
$23,500 $0 $23,500 $26,522 $26,522 $-3,022
Construction
$26,800 $-2,712 $24,088 $24,193 $24,193 $-105
 
Total* $52,960 $-2,712 $50,248 $53,792 $53,792 $-3,544

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2006 

06/01/2006 
 

 
01/01/2006 

06/01/2006 
100  01/01/2006 

06/28/2006 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

08/01/2008 
 

10/15/2009 
07/01/2007 

09/01/2009 
100  07/01/2006 

09/24/2009 
12 

-1 
Begin Right of Way Phase

End Right of Way Phase
08/01/2006 

02/01/2009 
 

10/15/2009 
08/01/2006 

06/01/2009 
100  08/01/2006 

02/26/2013 


-46 
Begin Construction Phase

End Construction Phase
03/01/2009 

08/01/2010 
10/15/2009 

10/15/2009 
02/01/2010 

01/01/2012 
100  12/01/2009 

08/30/2012 


-8 
Begin Closeout Phase

End Closeout Phase
08/01/2010 

02/01/2011 
 

 
08/30/2010 

02/28/2011 
100  08/30/2012 

11/27/2013 
-24 

-33 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
$20,000,000
Current Approved:
$17,158,806
Actual Expenditures:
$17,158,806

 

Status as of December 31, 2023.