Streeter Avenue Grade Separation |
Description: Construct Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Riverside |
Zip Code | 92504 |
Senate District |
31 |
Assembly District | 64 |
Congressional District | 44 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Design (PS&E) Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Right of Way Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Construction Phase |
City of Riverside | Farshid Mohammadi | (951) 826-5515 | fmohammadi@riversideca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$15,500 | $0 | $15,500 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,000 | $5,312 | $10,312 | ||||
Local** |
$16,300 | $-6,112 | $10,188 | ||||
Total**** | $36,800 | $-800 | $36,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,500 | $0 | $1,500 | $1,195 | $1,195 | $305 | |
Design(PS&E) |
$1,000 | $0 | $1,000 | $1,435 | $1,435 | $-435 | |
Right of Way |
$14,300 | $-6,800 | $7,500 | $4,994 | $4,994 | $2,506 | |
Construction |
$20,000 | $6,000 | $26,000 | $23,138 | $23,138 | $2,862 | |
Total* | $36,800 | $-800 | $36,000 | $30,763 | $30,763 | $5,237 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/01/2008 01/01/2010 |
06/27/2012 |
02/01/2008 02/08/2010 |
100 | 02/01/2008 02/08/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2010 10/01/2011 |
06/27/2012 06/27/2012 |
02/08/2010 07/01/2012 |
100 | 02/08/2010 07/01/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2010 10/01/2011 |
06/27/2012 06/27/2012 |
02/08/2010 06/01/2012 |
100 | 02/08/2010 06/01/2012 |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2012 07/01/2013 |
06/27/2012 06/27/2012 |
11/30/2012 05/30/2014 |
100 | 10/23/2012 08/20/2015 |
1 -15 |
Begin Closeout Phase
End Closeout Phase |
07/01/2013 10/01/2013 |
06/27/2012 |
05/30/2014 11/30/2014 |
100 | 08/20/2015 08/22/2019 |
-15 -58 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$15,500,000 |
Current Approved: |
$15,500,000 |
Actual Expenditures: |
$13,507,000 |
Status as of December 31, 2023.