Streeter Avenue Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92504
 
Senate District
31
Assembly District 64
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Design (PS&E) Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Right of Way Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
Construction Phase
City of Riverside Farshid Mohammadi (951) 826-5515   fmohammadi@riversideca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$15,500 $0 $15,500
Non-bond Funding
State/Federal*
$5,000 $5,312 $10,312
Local**
$16,300 $-6,112 $10,188
 
Total**** $36,800 $-800 $36,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,500 $0 $1,500 $1,195 $1,195 $305
Design(PS&E)
$1,000 $0 $1,000 $1,435 $1,435 $-435
Right of Way
$14,300 $-6,800 $7,500 $4,994 $4,994 $2,506
Construction
$20,000 $6,000 $26,000 $23,138 $23,138 $2,862
 
Total* $36,800 $-800 $36,000 $30,763 $30,763 $5,237

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2008 

01/01/2010 
 

06/27/2012 
02/01/2008 

02/08/2010 
100  02/01/2008 

02/08/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

10/01/2011 
06/27/2012 

06/27/2012 
02/08/2010 

07/01/2012 
100  02/08/2010 

07/01/2012 


Begin Right of Way Phase

End Right of Way Phase
01/01/2010 

10/01/2011 
06/27/2012 

06/27/2012 
02/08/2010 

06/01/2012 
100  02/08/2010 

06/01/2012 


Begin Construction Phase

End Construction Phase
01/01/2012 

07/01/2013 
06/27/2012 

06/27/2012 
11/30/2012 

05/30/2014 
100  10/23/2012 

08/20/2015 


-15 
Begin Closeout Phase

End Closeout Phase
07/01/2013 

10/01/2013 
06/27/2012 

 
05/30/2014 

11/30/2014 
100  08/20/2015 

08/22/2019 
-15 

-58 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$15,500,000
Current Approved:
$15,500,000
Actual Expenditures:
$13,507,000

 

Status as of December 31, 2023.