I-580 Truck Climbing Lane |
Description: Construct New Truck Climbing Lane
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | Livermore |
Zip Code | |
Senate District |
07 |
Assembly District | 15 |
Congressional District | 10 |
Caltrans District |
04 |
County/State Route | Alameda 580 |
Postmile Begin/End | 4.9 8.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Truck Climbing Lane Miles | 3.3 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Issa Bouri | (510)286-5220 | issa_bouri@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Issa Bouri | (510)286-5220 | issa_bouri@dot.ca.gov | |
Right of Way Phase |
Caltrans | Issa Bouri | (510)286-5220 | issa_bouri@dot.ca.gov | |
Construction Phase |
Caltrans | Issa Bouri | (510)286-5220 | issa_bouri@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$64,265 | $-19,362 | $44,903 | ||||
Non-bond Funding | |||||||
Total**** | $64,265 | $-19,362 | $44,903 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$2,490 | $0 | $2,490 | $2,490 | $0 | $2,490 | |
Design(PS&E) |
$5,140 | $0 | $5,140 | $4,627 | $0 | $5,140 | |
Right of Way |
$105 | $0 | $105 | $15 | $0 | $105 | |
Construction |
$56,530 | $-19,362 | $37,168 | $37,168 | $0 | $37,168 | |
Total* | $64,265 | $-19,362 | $44,903 | $44,300 | $0 | $44,903 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/01/2008 01/31/2010 |
|
08/01/2008 01/31/2010 |
100 | 08/01/2008 01/31/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2010 08/01/2011 |
|
02/01/2010 08/01/2011 |
100 | 02/01/2010 08/01/2011 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
02/01/2010 08/01/2011 |
|
02/01/2010 08/01/2011 |
100 | 02/01/2010 01/31/2013 |
0 -18 |
Begin Construction Phase
End Construction Phase |
02/01/2012 02/01/2014 |
01/25/2012 10/24/2012 |
06/01/2012 04/01/2015 |
100 | 06/18/2012 10/31/2016 |
-1 -19 |
Begin Closeout Phase
End Closeout Phase |
03/01/2014 12/01/2014 |
10/24/2012 |
06/01/2015 12/01/2015 |
50 | 10/31/2016 07/29/2017 |
-17 -20 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Truck Climbing Lane Miles | 3.3 |
Bond Funding Cost | |
---|---|
Adopted: |
$64,265,000 |
Current Approved: |
$44,903,000 |
Actual Expenditures: |
$44,903,000 |
Status as of December 31, 2023.