I-580 Truck Climbing Lane

Description: Construct New Truck Climbing Lane

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Livermore
Zip Code
 
Senate District
07
Assembly District 15
Congressional District 10
 
Caltrans District
04
 
 
County/State Route Alameda 580
Postmile Begin/End 4.9 8.2
Project Benefits
 Benefit Baseline Actual
Truck Climbing Lane Miles  3.3      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Issa Bouri (510)286-5220   issa_bouri@dot.ca.gov
Design (PS&E) Phase
Caltrans Issa Bouri (510)286-5220   issa_bouri@dot.ca.gov
Right of Way Phase
Caltrans Issa Bouri (510)286-5220   issa_bouri@dot.ca.gov
Construction Phase
Caltrans Issa Bouri (510)286-5220   issa_bouri@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$64,265 $-19,362 $44,903
Non-bond Funding
 
Total**** $64,265 $-19,362 $44,903

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,490 $0 $2,490 $2,490 $0 $2,490
Design(PS&E)
$5,140 $0 $5,140 $4,627 $0 $5,140
Right of Way
$105 $0 $105 $15 $0 $105
Construction
$56,530 $-19,362 $37,168 $37,168 $0 $37,168
 
Total* $64,265 $-19,362 $44,903 $44,300 $0 $44,903

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2008 

01/31/2010 
 

 
08/01/2008 

01/31/2010 
100  08/01/2008 

01/31/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2010 

08/01/2011 
 

 
02/01/2010 

08/01/2011 
100  02/01/2010 

08/01/2011 


Begin Right of Way Phase

End Right of Way Phase
02/01/2010 

08/01/2011 
 

 
02/01/2010 

08/01/2011 
100  02/01/2010 

01/31/2013 


-18 
Begin Construction Phase

End Construction Phase
02/01/2012 

02/01/2014 
01/25/2012 

10/24/2012 
06/01/2012 

04/01/2015 
100  06/18/2012 

10/31/2016 
-1 

-19 
Begin Closeout Phase

End Closeout Phase
03/01/2014 

12/01/2014 
10/24/2012 

 
06/01/2015 

12/01/2015 
50  10/31/2016 

07/29/2017 
-17 

-20 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Truck Climbing Lane Miles 3.3

Bond Funding Cost
Adopted:
$64,265,000
Current Approved:
$44,903,000
Actual Expenditures:
$44,903,000

 

Status as of December 31, 2023.