Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Clay Street Grade Separation |
Description: Construct Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | |
Zip Code | |
Senate District |
31 |
Assembly District | 60, 61 |
Congressional District | 41 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
County of Riverside | Scott Staley | (951) 955-2092 | cstaley@rivco.org | |
Design (PS&E) Phase |
County of Riverside | Scott Staley | (951) 955-2092 | cstaley@rivco.org | |
Right of Way Phase |
County of Riverside | Scott Staley | (951) 955-2092 | cstaley@rivco.org | |
Construction Phase |
County of Riverside | Scott Staley | (951) 955-2092 | cstaley@rivco.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$12,500 | $747 | $13,247 | ||||
Non-bond Funding | |||||||
State/Federal* |
$15,000 | $-12,500 | $2,500 | ||||
Local** |
$9,850 | $5,209 | $15,059 | ||||
Total**** | $37,350 | $-6,544 | $30,806 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,125 | $-623 | $502 | $449 | $449 | $53 | |
Design(PS&E) |
$4,325 | $-1,482 | $2,843 | $3,327 | $3,327 | $-484 | |
Right of Way |
$2,000 | $5,385 | $7,385 | $10,980 | $10,980 | $-3,595 | |
Construction |
$29,900 | $-9,824 | $20,076 | $20,285 | $20,285 | $-209 | |
Total* | $37,350 | $-6,544 | $30,806 | $35,041 | $35,041 | $-4,235 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/08/2008 04/30/2010 |
12/06/2012 12/06/2012 |
06/02/2009 01/14/2011 |
100 | 06/08/2009 03/15/2011 |
0 -2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/03/2010 06/30/2011 |
12/06/2012 06/11/2013 |
02/02/2011 03/29/2013 |
100 | 03/15/2011 05/15/2013 |
-1 -2 |
Begin Right of Way Phase
End Right of Way Phase |
09/30/2010 09/30/2011 |
12/06/2012 06/11/2013 |
03/01/2011 05/30/2013 |
100 | 03/01/2011 05/30/2013 |
0 0 |
Begin Construction Phase
End Construction Phase |
03/30/2012 09/30/2013 |
06/11/2013 06/11/2013 |
12/01/2013 06/15/2016 |
100 | 12/17/2013 05/02/2017 |
-1 -11 |
Begin Closeout Phase
End Closeout Phase |
10/01/2013 12/31/2013 |
06/11/2013 |
08/15/2016 12/15/2016 |
100 | 05/09/2018 11/15/2018 |
-21 -23 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 | |
Rail/Highway At-Grade Crossings Eliminated | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$12,500,000 |
Current Approved: |
$13,107,679 |
Actual Expenditures: |
$13,107,679 |
Status as of December 31, 2023.