Clay Street Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City
Zip Code
 
Senate District
31
Assembly District 60, 61
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
Design (PS&E) Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
Right of Way Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
Construction Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$12,500 $747 $13,247
Non-bond Funding
State/Federal*
$15,000 $-12,500 $2,500
Local**
$9,850 $5,209 $15,059
 
Total**** $37,350 $-6,544 $30,806

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,125 $-623 $502 $449 $449 $53
Design(PS&E)
$4,325 $-1,482 $2,843 $3,327 $3,327 $-484
Right of Way
$2,000 $5,385 $7,385 $10,980 $10,980 $-3,595
Construction
$29,900 $-9,824 $20,076 $20,285 $20,285 $-209
 
Total* $37,350 $-6,544 $30,806 $35,041 $35,041 $-4,235

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/08/2008 

04/30/2010 
12/06/2012 

12/06/2012 
06/02/2009 

01/14/2011 
100  06/08/2009 

03/15/2011 


-2 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/03/2010 

06/30/2011 
12/06/2012 

06/11/2013 
02/02/2011 

03/29/2013 
100  03/15/2011 

05/15/2013 
-1 

-2 
Begin Right of Way Phase

End Right of Way Phase
09/30/2010 

09/30/2011 
12/06/2012 

06/11/2013 
03/01/2011 

05/30/2013 
100  03/01/2011 

05/30/2013 


Begin Construction Phase

End Construction Phase
03/30/2012 

09/30/2013 
06/11/2013 

06/11/2013 
12/01/2013 

06/15/2016 
100  12/17/2013 

05/02/2017 
-1 

-11 
Begin Closeout Phase

End Closeout Phase
10/01/2013 

12/31/2013 
06/11/2013 

 
08/15/2016 

12/15/2016 
100  05/09/2018 

11/15/2018 
-21 

-23 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$12,500,000
Current Approved:
$13,107,679
Actual Expenditures:
$13,107,679

Click to view the Final Audit Report

 

Status as of December 31, 2023.